ITAC Assessment: WV0487
ITAC logo
ITAC Assessment: WV0487
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Engines and Transmissions
NAICS 336350: Motor Vehicle Transmission and Power Train Parts Manufacturing
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $100
M
to 500
M
# of Employees 500
Plant Area 1,500,000
ft2
Annual Production 66,000
units
Production Hrs. Annual 4,160
hrs
Location (State) Maryland

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,197,154 40,057,049
kWh
Electricity Demand $169,451 78,336
kW-mo/yr
Natural Gas $995,332 192,198
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $173,614 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $39,768

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings
01 2.1221: Replace obsolete burners with more efficient ones $83,149 $50,000 - - - $83,149
-
MMBtu
-
02 2.2424: Use heat in flue gases to preheat products or materials $34,136 $82,440 - - - $34,136
-
MMBtu
-
03 2.3212: Optimize plant power factor $12,000 $56,000 - - $12,000 - -
04 2.4224: Upgrade controls on compressors $10,990 $7,560 $10,990
200,329
kWh
- - - -
05 2.4157: Establish a predictive maintenance program $9,081 $1,000 $12,456
227,044
kWh
$1,415
-
kW-mo/yr
- - $(-4,790.0)
06 2.7135: Install occupancy sensors $5,633 $2,520 $5,633
102,675
kWh
- - - -
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $4,533 - $4,071
74,215
kWh
$462
-
kW-mo/yr
- - -
08 2.2625: Chill water to the highest temperature possible $2,271 $210 $2,040
37,193
kWh
$231
-
kW-mo/yr
- - -
09 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,002 $3,401 $1,799
32,790
kWh
$203
-
kW-mo/yr
- - -
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,857 $570 $1,667
30,382
kWh
$190
-
kW-mo/yr
- - -
11 2.7261: Install timers and/or thermostats $1,698 $1,760 $1,525
27,800
kWh
$173
-
kW-mo/yr
- - -
12 2.4151: Develop a repair/replace policy $1,457 $1,334 $1,812
33,025
kWh
$205
-
kW-mo/yr
- - $(-560.0)
13 2.4231: Reduce the pressure of compressed air to the minimum required $1,419 $70 $1,274
23,215
kWh
$145
-
kW-mo/yr
- - -
14 2.4221: Install compressor air intakes in coolest locations $1,359 $487 $1,221
22,261
kWh
$138
-
kW-mo/yr
- - -
15 2.1233: Analyze flue gas for proper air/fuel ratio $931 $2,000 - - - $1,036
-
MMBtu
$(-105.0)
16 2.2511: Insulate bare equipment $564 $2,006 - - - $564
-
MMBtu
-
17 2.4239: Eliminate or reduce compressed air usage $534 $792 $480
8,754
kWh
$54
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $173,614 $212,150 $44,968
819,683
kWh
$3,216
-
kW-mo/yr
$12,000 $118,885
-
MMBtu
$(-5,455.0)
TOTAL IMPLEMENTED $39,768 $21,013 $41,707
760,229
kWh
$2,847
-
kW-mo/yr
- $564
-
MMBtu
$(-5,350.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs