ITAC Assessment: ME0169
ITAC logo
ITAC Assessment: ME0169
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Textiles
NAICS
n/a
SIC 2542: Office and Store Fixtures, Partitions, Shelving, and Lockers, Except Wood
Sales Range $10
M
to 50
M
# of Employees 1,175
Plant Area 423,712
ft2
Annual Production 9,308,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,451,047 16,418,816
kWh
Fuel Oil #2 $16,443 3,877
MMBtu
Wood $238,045 160,381
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $118,115 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,124

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Wood Savings Administrative Changes Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $65,514 $27,280 $65,514
358,441
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $21,341 $28,606 $21,341
274,619
kWh
- -
03 2.3511: Use plant owned transformers or lease transformers $18,499 $75,000 - - $18,499
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,642 $1,200 $4,642
66,237
kWh
- -
05 2.4221: Install compressor air intakes in coolest locations $3,475 $1,000 $3,475
49,824
kWh
- -
06 2.1113: Reduce combustion air flow to optimum $2,205 $400 - $2,205
-
MMBtu
-
07 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,520 - $1,520
24,033
kWh
- -
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $919 $1,000 $919
13,189
kWh
- -
09 3.5212: Regrind, reuse, or sell scrap plastic parts - - - - -
TOTAL RECOMMENDED $118,115 $134,486 $97,411
786,343
kWh
$2,205
-
MMBtu
$18,499
TOTAL IMPLEMENTED $3,124 $1,400 $919
13,189
kWh
$2,205
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Wood Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs