| Assessment Year | 2013 |
|---|---|
| Principal Product | Bakeware and kitchen tools |
| NAICS | 332431: Metal Can Manufacturing |
| SIC | 3411: Metal Cans |
| Sales Range | $10 M to 50M |
| # of Employees | 165 |
| Plant Area |
137,535
ft2
|
| Annual Production | 500,000
ton
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $170,942 | 1,975,080 |
kWh
|
$0.087 |
| Electricity Demand | $56,480 | 8,280 |
kW-mo/yr
|
$6.82 |
| Natural Gas | $41,691 | 7,026 |
MMBtu
|
$5.93 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $49,874 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $33,467 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4224: Upgrade controls on compressors | $10,534 | $27,000 |
$8,582
99,209
kWh
|
$1,952
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $8,009 | $3,749 |
$6,522
75,400
kWh
|
$1,487
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $6,454 | $6,210 |
$(-49.0)
(-564)
kWh
|
$(-20.0)
-
kW-mo/yr
|
- |
$6,523
-
MMBtu
|
- | |
| 04 | 2.8112: Combine utility meters | $5,415 | $11,000 | - | - | $5,415 | - | - | |
| 05 | 2.4157: Establish a predictive maintenance program | $5,088 | $1,000 |
$4,771
55,157
kWh
|
$2,169
-
kW-mo/yr
|
- | - | $(-1,852.0) | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,860 | $310 |
$3,960
45,775
kWh
|
$900
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,543 | - |
$2,561
29,608
kWh
|
$982
-
kW-mo/yr
|
- | - | - | |
| 08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,944 | $3,375 |
$1,944
22,471
kWh
|
- | - | - | - | |
| 09 | 2.7135: Install occupancy sensors | $1,731 | $680 |
$1,410
16,298
kWh
|
$321
-
kW-mo/yr
|
- | - | - | |
| 10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,159 | $4,625 |
$954
11,033
kWh
|
$205
-
kW-mo/yr
|
- | - | - | |
| 11 | 2.4231: Reduce the pressure of compressed air to the minimum required | $716 | $105 |
$532
6,154
kWh
|
$184
-
kW-mo/yr
|
- | - | - | |
| 12 | 2.7122: Disconnect ballasts | $297 | $70 |
$242
2,796
kWh
|
$55
-
kW-mo/yr
|
- | - | - | |
| 13 | 2.4151: Develop a repair/replace policy | $124 | $426 |
$168
1,947
kWh
|
$61
-
kW-mo/yr
|
- | - | $(-105.0) | |
| TOTAL RECOMMENDED | $49,874 | $58,550 |
$31,597
365,284
kWh
|
$8,296
-
kW-mo/yr
|
$5,415 |
$6,523
-
MMBtu
|
$(-1,957.0) | ||
| TOTAL IMPLEMENTED | $33,467 | $45,216 |
$23,180
267,977
kWh
|
$6,829
-
kW-mo/yr
|
$5,415 | - | $(-1,957.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs