ITAC Assessment: WV0438
ITAC logo
ITAC Assessment: WV0438
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Recycled Aluminum
NAICS 331314: Secondary Smelting and Alloying of Aluminum
SIC 3341: Secondary Smelting and Refining of Nonferrous Metals
Sales Range $10
M
to 50
M
# of Employees 74
Plant Area 200,000
ft2
Annual Production 366,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $416,750 10,937,315
kWh
Electricity Demand $269,285 18,579
kW-mo/yr
Natural Gas $711,804 131,229
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $149,863 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $46,230

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $39,104 $107,167 $27,106
699,886
kWh
$11,998
-
kW-mo/yr
- -
02 2.2414: Use waste heat from hot flue gases to preheat $26,986 $25,242 - - $26,986
-
MMBtu
-
03 2.2424: Use heat in flue gases to preheat products or materials $23,750 $68,377 - - $23,750
-
MMBtu
-
04 2.4156: Establish a preventative maintenance program $14,539 $4,000 $9,726
251,113
kWh
$4,985
-
kW-mo/yr
- $(-172.0)
05 2.7142: Utilize higher efficiency lamps and/or ballasts $12,808 $24,313 $7,968
205,738
kWh
$4,840
-
kW-mo/yr
- -
06 2.2511: Insulate bare equipment $10,092 $2,424 - - $10,092
-
MMBtu
-
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $8,963 $2,000 $5,926
153,021
kWh
$3,037
-
kW-mo/yr
- -
08 2.4151: Develop a repair/replace policy $8,588 $629 $5,806
149,918
kWh
$2,970
-
kW-mo/yr
- $(-188.0)
09 2.4221: Install compressor air intakes in coolest locations $2,774 $648 $1,832
47,306
kWh
$942
-
kW-mo/yr
- -
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,332 $359 $883
22,807
kWh
$449
-
kW-mo/yr
- -
11 2.6232: Install set-back timers $927 $617 - - $927
-
MMBtu
-
TOTAL RECOMMENDED $149,863 $235,776 $59,247
1,529,789
kWh
$29,221
-
kW-mo/yr
$61,755
-
MMBtu
$(-360.0)
TOTAL IMPLEMENTED $46,230 $31,301 $30,309
782,597
kWh
$16,281
-
kW-mo/yr
- $(-360.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs