ITAC Assessment: WV0433
ITAC logo
ITAC Assessment: WV0433
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Copper alloy strips
NAICS 332323: Ornamental and Architectural Metal Work Manufacturing
SIC 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 50
Plant Area 63,000
ft2
Annual Production 24,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $114,445 2,824,920
kWh
Electricity Demand $130,447 6,392
kW-mo/yr
Natural Gas $53,235 8,427
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,787 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,340

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.4224: Upgrade controls on compressors $4,732 $16,000 $3,801
93,931
kWh
$931
-
kW-mo/yr
- -
02 2.2136: Install / repair insulation on steam lines $3,343 $2,009 - - $3,343
-
MMBtu
-
03 2.4133: Use most efficient type of electric motors $3,088 $1,625 $1,738
42,924
kWh
$1,650
-
kW-mo/yr
- $(-300.0)
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,813 - $1,401
34,593
kWh
$1,412
-
kW-mo/yr
- -
05 2.4151: Develop a repair/replace policy $2,048 $2,000 $1,478
36,485
kWh
$1,403
-
kW-mo/yr
- $(-833.0)
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,487 $4,365 $403
9,950
kWh
$1,084
-
kW-mo/yr
- -
07 2.1233: Analyze flue gas for proper air/fuel ratio $1,292 $1,000 - - $1,542
-
MMBtu
$(-250.0)
08 2.4231: Reduce the pressure of compressed air to the minimum required $950 $100 $562
13,879
kWh
$388
-
kW-mo/yr
- -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $894 $340 $527
13,005
kWh
$367
-
kW-mo/yr
- -
10 2.7261: Install timers and/or thermostats $872 $600 - - $872
-
MMBtu
-
11 2.4221: Install compressor air intakes in coolest locations $737 $3,325 $431
10,644
kWh
$306
-
kW-mo/yr
- -
12 2.2414: Use waste heat from hot flue gases to preheat $531 $6,150 - - $531
-
MMBtu
-
TOTAL RECOMMENDED $22,787 $37,514 $10,341
255,411
kWh
$7,541
-
kW-mo/yr
$6,288
-
MMBtu
$(-1,383.0)
TOTAL IMPLEMENTED $11,340 $5,449 $3,968
97,962
kWh
$3,570
-
kW-mo/yr
$4,885
-
MMBtu
$(-1,083.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs