ITAC Assessment: WV0413
ITAC logo
ITAC Assessment: WV0413
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product aluminium windows and doors
NAICS 332321: Metal Window and Door Manufacturing
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $100
M
to 500
M
# of Employees 900
Plant Area 900,000
ft2
Annual Production 2,160
Tgal
Production Hrs. Annual 6,120
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,622,448 22,318,638
kWh
Natural Gas $662,877 127,004
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $463,677 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $201,014

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4322: Use or replace with energy efficient substitutes $108,743 $89,900 - $108,743
-
MMBtu
- -
02 2.2414: Use waste heat from hot flue gases to preheat $89,967 $129,542 - $89,967
-
MMBtu
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $77,291 $154,121 $77,291
1,063,300
kWh
- - -
04 2.2628: Utilize a less expensive cooling method $59,435 $55,000 $59,435
817,656
kWh
- - -
05 2.2514: Cover open tanks $41,697 $9,404 - $41,697
-
MMBtu
- -
06 2.2426: Use waste heat from flue gases to heat space conditioning air $24,889 $9,534 $(-353.0)
(-4,851)
kWh
$25,317
-
MMBtu
$(-75.0) -
07 2.6212: Turn off equipment during breaks, reduce operating time $14,418 - - $14,418
-
MMBtu
- -
08 2.2437: Recover waste heat from equipment $12,163 $1,048 - $12,163
-
MMBtu
- -
09 2.4151: Develop a repair/replace policy $10,138 $1,674 $12,448
171,247
kWh
- $(-2,310.0) -
10 2.6231: Utilize controls to operate equipment only when needed $6,565 $7,770 $6,565
90,313
kWh
- - -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $6,414 - $9,164
126,074
kWh
- - $(-2,750.0)
12 2.7142: Utilize higher efficiency lamps and/or ballasts $4,242 $16,759 $4,242
58,351
kWh
- - -
13 2.4221: Install compressor air intakes in coolest locations $3,528 $1,876 $3,528
48,538
kWh
- - -
14 2.4239: Eliminate or reduce compressed air usage $2,830 $6,571 $2,830
38,939
kWh
- - -
15 2.1233: Analyze flue gas for proper air/fuel ratio $1,069 $1,000 - $1,300
-
MMBtu
$(-231.0) -
16 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $288 $357 $288
3,961
kWh
- - -
TOTAL RECOMMENDED $463,677 $484,556 $175,438
2,413,528
kWh
$293,605
-
MMBtu
$(-2,616.0) $(-2,750.0)
TOTAL IMPLEMENTED $201,014 $245,016 $165,345
2,274,677
kWh
$41,035
-
MMBtu
$(-2,616.0) $(-2,750.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs