Assessment Year | 2008 |
---|---|
Principal Product | Industrial Material Handling Products |
NAICS | 337215: Showcase, Partition, Shelving, and Locker Manufacturing |
SIC | 3559: Special Industry Machinery, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 185 |
Plant Area |
330,000
ft2
|
Annual Production | 1,000,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $444,969 | 7,696,391 |
kWh
|
$0.058 |
Electricity Demand | $159,359 | 16,644 |
kW-mo/yr
|
$9.57 |
Natural Gas | $188,846 | 17,248 |
MMBtu
|
$10.95 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $129,560 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $55,453 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $40,090 | $4,000 | - | - |
$40,165
-
MMBtu
|
$(-75.0) | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $34,198 | $81,425 |
$23,269
402,438
kWh
|
$10,929
-
kW-mo/yr
|
- | - | - | |
03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $14,879 | $21,600 |
$(-3,906.0)
67,548
kWh
|
$(-1,330.0)
-
kW-mo/yr
|
$20,115
-
MMBtu
|
- | - | |
04 | 2.7313: Recycle air for heating, ventilation and air conditioning | $14,783 | $5,000 | - | - |
$14,783
-
MMBtu
|
- | - | |
05 | 2.4155: Standardize motor inventory | $6,638 | $763 |
$5,573
96,377
kWh
|
$1,365
-
kW-mo/yr
|
- | $(-300.0) | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,599 | $548 |
$3,824
66,138
kWh
|
$775
-
kW-mo/yr
|
- | - | - | |
07 | 2.2511: Insulate bare equipment | $3,100 | $140 |
$2,526
43,689
kWh
|
$574
-
kW-mo/yr
|
- | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,980 | - |
$1,526
26,408
kWh
|
$1,454
-
kW-mo/yr
|
- | - | - | |
09 | 2.4312: Improve lubrication practices | $2,864 | $2,950 |
$2,670
46,171
kWh
|
$632
-
kW-mo/yr
|
- | - | $(-438.0) | |
10 | 2.4239: Eliminate or reduce compressed air usage | $1,986 | $792 |
$665
11,493
kWh
|
$1,321
-
kW-mo/yr
|
- | - | - | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,425 | $4,393 |
$946
16,365
kWh
|
$479
-
kW-mo/yr
|
- | - | - | |
12 | 2.4221: Install compressor air intakes in coolest locations | $1,167 | $925 |
$727
12,567
kWh
|
$440
-
kW-mo/yr
|
- | - | - | |
13 | 2.4231: Reduce the pressure of compressed air to the minimum required | $527 | $100 |
$326
5,641
kWh
|
$201
-
kW-mo/yr
|
- | - | - | |
14 | 2.2625: Chill water to the highest temperature possible | $324 | $50 |
$266
4,597
kWh
|
$58
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $129,560 | $122,686 |
$38,412
799,432
kWh
|
$16,898
-
kW-mo/yr
|
$75,063
-
MMBtu
|
$(-375.0) | $(-438.0) | ||
TOTAL IMPLEMENTED | $55,453 | $88,161 |
$38,655
668,549
kWh
|
$17,098
-
kW-mo/yr
|
- | $(-300.0) | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs