ITAC Assessment: WV0374
ITAC logo
ITAC Assessment: WV0374
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Cutting Tools
NAICS 332216: Saw Blade and Handtool Manufacturing
SIC 3545: Cutting Tools, Machine Tool Accessories, and Machinists' Precision Measuring Devices
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 74,000
ft2
Annual Production 1,820,000
pieces
Production Hrs. Annual 8,712
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $804,089 10,379,000
kWh
Natural Gas $7,175 3,181
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $82,864 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $64,900

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Personnel Changes Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $25,144 $12,730 $25,144
324,567
kWh
- -
02 2.4239: Eliminate or reduce compressed air usage $15,831 $2,213 $15,831
204,351
kWh
- -
03 2.4157: Establish a predictive maintenance program $7,994 $4,500 $8,378
108,144
kWh
- $(-384.0)
04 2.4151: Develop a repair/replace policy $7,339 $1,076 $7,447
96,127
kWh
- $(-108.0)
05 2.3212: Optimize plant power factor $5,562 $11,346 $5,562
-
kWh
- -
06 2.4231: Reduce the pressure of compressed air to the minimum required $5,079 $6,378 $5,619
72,534
kWh
- $(-540.0)
07 2.7135: Install occupancy sensors $4,440 $612 $4,440
57,317
kWh
- -
08 2.4221: Install compressor air intakes in coolest locations $3,513 $315 $3,513
45,345
kWh
- -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $3,039 $9,054 $3,039
39,232
kWh
- -
10 2.2437: Recover waste heat from equipment $2,784 $440 - $2,784
-
MMBtu
-
11 2.2628: Utilize a less expensive cooling method $1,750 $1,884 $2,066
26,663
kWh
- $(-316.0)
12 2.6231: Utilize controls to operate equipment only when needed $389 $690 - $389
-
MMBtu
-
TOTAL RECOMMENDED $82,864 $51,238 $81,039
974,280
kWh
$3,173
-
MMBtu
$(-1,348.0)
TOTAL IMPLEMENTED $64,900 $27,212 $65,932
851,068
kWh
- $(-1,032.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs