ITAC Assessment: WV0362
ITAC logo
ITAC Assessment: WV0362
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Fiber Glass Media
NAICS 327993: Mineral Wool Manufacturing
SIC 3296: Mineral Wool
Sales Range $10
M
to 50
M
# of Employees 125
Plant Area 110,000
ft2
Annual Production 14,000,000
lb
Production Hrs. Annual 8,568
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $90,457 3,273,953
kWh
Electricity Demand $52,973 5,437
kW-mo/yr
Electricity Fees $5,475 -
Natural Gas $991,322 94,941
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $114,944 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,605

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2511: Insulate bare equipment $80,064 $26,135 - - $80,064
-
MMBtu
02 2.2414: Use waste heat from hot flue gases to preheat $10,461 $13,900 - - $10,461
-
MMBtu
03 2.1233: Analyze flue gas for proper air/fuel ratio $4,679 $2,000 - - $4,679
-
MMBtu
04 2.2437: Recover waste heat from equipment $3,748 $660 - - $3,748
-
MMBtu
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,397 - $2,192
75,008
kWh
$1,205
-
kW-mo/yr
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,787 - $1,051
35,866
kWh
$736
-
kW-mo/yr
-
07 2.7124: Make a practice of turning off lights when not needed $1,693 $1,500 $1,155
39,413
kWh
$538
-
kW-mo/yr
-
08 2.4151: Develop a repair/replace policy $1,851 $185 $1,195
40,780
kWh
$656
-
kW-mo/yr
-
09 2.4157: Establish a predictive maintenance program $1,851 $1,000 $1,195
40,780
kWh
$656
-
kW-mo/yr
-
10 2.7142: Utilize higher efficiency lamps and/or ballasts $1,521 $978 $722
24,652
kWh
$799
-
kW-mo/yr
-
11 2.4221: Install compressor air intakes in coolest locations $1,387 $224 $1,056
36,049
kWh
$331
-
kW-mo/yr
-
12 2.2511: Insulate bare equipment $1,295 $740 - - $1,295
-
MMBtu
13 2.4231: Reduce the pressure of compressed air to the minimum required $913 $20 $623
21,265
kWh
$290
-
kW-mo/yr
-
14 2.4239: Eliminate or reduce compressed air usage $297 $400 $229
7,800
kWh
$68
-
kW-mo/yr
-
TOTAL RECOMMENDED $114,944 $47,742 $9,418
321,613
kWh
$5,279
-
kW-mo/yr
$100,247
-
MMBtu
TOTAL IMPLEMENTED $14,605 $4,823 $8,362
285,564
kWh
$4,948
-
kW-mo/yr
$1,295
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs