| Assessment Year | 2001 |
|---|---|
| Principal Product | Closed cell foam |
| NAICS |
n/a
|
| SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 126 |
| Plant Area |
230,000
ft2
|
| Annual Production | 11,000
thousand feet
|
| Production Hrs. Annual | 3,640
hrs
|
| Location (State) | West Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $115,778 | 1,965,208 |
kWh
|
$0.059 |
| Natural Gas | $30,775 | 4,793 |
MMBtu
|
$6.42 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $82,448 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $48,299 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $535 | $188 |
$535
9,083
kWh
|
- | - | - | - | |
| 02 | 2.7241: Install outside air damper / economizer on hvac unit | $15,768 | $13,800 |
$15,768
267,802
kWh
|
- | - | - | - | |
| 03 | 2.2628: Utilize a less expensive cooling method | $1,519 | $1,362 |
$1,519
25,784
kWh
|
- | - | - | - | |
| 04 | 2.2625: Chill water to the highest temperature possible | $121 | $60 |
$121
2,051
kWh
|
- | - | - | - | |
| 05 | 2.7496: Install partitions to reduce size of conditioned space | $2,714 | $2,520 |
$2,714
45,708
kWh
|
- | - | - | - | |
| 06 | 2.7111: Reduce illumination to minimum necessary levels | $5,713 | $1,440 |
$5,713
96,983
kWh
|
- | - | - | - | |
| 07 | 2.2511: Insulate bare equipment | $1,985 | $276 |
$1,985
33,695
kWh
|
- | - | - | - | |
| 08 | 2.2511: Insulate bare equipment | $3,625 | $730 |
$3,625
61,530
kWh
|
- | - | - | - | |
| 09 | 2.4157: Establish a predictive maintenance program | $1,088 | $1,200 |
$1,448
30,765
kWh
|
- | - | $(-360.0) | - | |
| 10 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $5,940 | - | - | - |
$5,940
-
lb
|
- | - | |
| 11 | 3.6192: Use a less expensive method of waste removal | $18,480 | $9,000 | - |
$18,480
-
lb
|
- | - | - | |
| 12 | 4.446: Automate finishing process | $24,960 | $1,600 | - | - | - | - | $24,960 | |
| TOTAL RECOMMENDED | $82,448 | $32,176 |
$33,428
573,401
kWh
|
$18,480
-
lb
|
$5,940
-
lb
|
$(-360.0) | $24,960 | ||
| TOTAL IMPLEMENTED | $48,299 | $27,868 |
$30,179
518,610
kWh
|
$18,480
-
lb
|
- | $(-360.0) | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs