ITAC Assessment: WI0510
ITAC logo
ITAC Assessment: WI0510
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Outboard engines
NAICS 333618: Other Engine Equipment Manufacturing
SIC 3732: Boat Building and Repairing
Sales Range $10
M
to 50
M
# of Employees 125
Plant Area 122,000
ft2
Annual Production 2,600
pieces
Production Hrs. Annual 2,250
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $94,756 2,492,999
kWh
Electricity Demand $63,561 8,269
kW-mo/yr
Natural Gas $71,521 7,422
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $65,952 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,433

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7261: Install timers and/or thermostats $12,014 - $567
14,206
kWh
$157
-
kW-mo/yr
$11,290
-
MMBtu
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $8,865 $2,000 $4,811
120,583
kWh
$4,054
-
kW-mo/yr
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $5,944 $23,000 $2,859
71,662
kWh
$3,085
-
kW-mo/yr
-
04 2.2437: Recover waste heat from equipment $4,554 $1,000 - - $4,554
-
MMBtu
05 2.7491: Insulate glazing, walls, ceilings, and roofs $32,657 $3,352 $32,657
32,657
kWh
- -
06 2.4221: Install compressor air intakes in coolest locations $1,135 $640 $808
20,258
kWh
$327
-
kW-mo/yr
-
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $443 $438 $190
4,759
kWh
$253
-
kW-mo/yr
-
08 2.6232: Install set-back timers $340 $100 - $340
-
kW-mo/yr
-
TOTAL RECOMMENDED $65,952 $30,530 $41,892
264,125
kWh
$8,216
-
kW-mo/yr
$15,844
-
MMBtu
TOTAL IMPLEMENTED $19,433 $23,740 $4,234
106,126
kWh
$3,909
-
kW-mo/yr
$11,290
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs