Assessment Year | 2005 |
---|---|
Principal Product | Flex Packaging |
NAICS | 322220: Paper Bag and Coated and Treated Paper Manufacturing |
SIC | 2672: Coated and Laminated Paper, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 75 |
Plant Area |
60,000
ft2
|
Annual Production | 4,399,069
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $374,474 | 10,979,797 |
kWh
|
$0.034 |
Electricity Demand | $264,277 | 30,088 |
kW-mo/yr
|
$8.78 |
Natural Gas | $108,884 | 12,685 |
MMBtu
|
$8.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $79,487 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 3.5212: Regrind, reuse, or sell scrap plastic parts | - | - | - | - | - | - | - | |
02 | 2.2414: Use waste heat from hot flue gases to preheat | $45,520 | $17,500 | - | - |
$45,520
-
MMBtu
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,079 | $20,340 |
$5,980
166,110
kWh
|
$3,099
-
kW-mo/yr
|
- | - | - | |
04 | 3.8142: Distill contaminated solvents for reuse | $11,414 | $21,105 |
$(-539.0)
(-25,800)
kWh
|
- | - |
$12,143
-
gal
|
$(-190.0)
-
Tgal
|
|
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,036 | $11,640 |
$5,036
139,880
kWh
|
- | - | - | - | |
06 | 2.7261: Install timers and/or thermostats | $3,268 | - |
$661
18,359
kWh
|
- |
$2,607
-
MMBtu
|
- | - | |
07 | 2.7251: Reduce air conditioning load by evaporating water from roof | $2,638 | $7,500 |
$1,628
45,219
kWh
|
$1,172
-
kW-mo/yr
|
- | - |
$(-162.0)
-
Tgal
|
|
08 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,161 | - | - |
$1,161
-
kW-mo/yr
|
- | - | - | |
09 | 2.4221: Install compressor air intakes in coolest locations | $862 | $640 |
$547
15,202
kWh
|
$315
-
kW-mo/yr
|
- | - | - | |
10 | 2.7135: Install occupancy sensors | $509 | $600 |
$509
14,151
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $79,487 | $79,325 |
$13,822
373,121
kWh
|
$5,747
-
kW-mo/yr
|
$48,127
-
MMBtu
|
$12,143
-
gal
|
$(-352.0)
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs