ITAC Assessment: UD0952
ITAC logo
ITAC Assessment: UD0952
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Encapsulated and Spray Dried Flavors
NAICS 311942: Spice and Extract Manufacturing
SIC 2087: Flavoring Extracts and Flavoring Syrups, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 250
Plant Area 217,000
ft2
Annual Production 3,900,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $645,493 12,621,300
kWh
Electricity Demand $213,728 24,480
kW-mo/yr
Electricity Fees $2,586 -
Natural Gas $269,212 42,716
MMBtu
Waste Disposal Costs
Water Usage $225,813 45,168,728
Tgal
Water Disposal $224,513 45,169
Tgal
TOTAL YEARLY COSTS $1,581,345
RECOMMENDED SAVINGS* $90,077 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $38,725

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (haz) Savings Administrative Changes Savings
01 2.8112: Combine utility meters $26,792 - - - $27,392 - - $(-600.0)
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $4,722 - $3,158
118,089
kWh
$1,564
-
kW-mo/yr
- - - -
03 2.2625: Chill water to the highest temperature possible $1,277 - $854
31,920
kWh
$423
-
kW-mo/yr
- - - -
04 2.1233: Analyze flue gas for proper air/fuel ratio $4,157 - - - - $4,157
-
MMBtu
- -
05 2.2123: Insulate feedwater tank $983 $509 - - - $983
-
MMBtu
- -
06 2.1222: Install turbulators $6,373 $3,750 - - - $6,373
-
MMBtu
- -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,764 $1,000 $2,491
93,143
kWh
$1,233
-
kW-mo/yr
- - - $(-960.0)
08 2.4224: Upgrade controls on compressors $1,652 $800 $1,652
61,729
kWh
- - - - -
09 2.7135: Install occupancy sensors $10,838 $19,760 $8,963
335,193
kWh
- - - - $1,875
10 2.7142: Utilize higher efficiency lamps and/or ballasts $2,795 $12,240 $2,077
77,656
kWh
$1,028
-
kW-mo/yr
- - - $(-310.0)
11 2.7122: Disconnect ballasts $546 $80 $320
11,975
kWh
$159
-
kW-mo/yr
- - - $67
12 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air $9,559 $23,200 - - - $9,559
-
MMBtu
- -
13 3.6112: Use filter and drying oven to reduce sludge volume $17,619 $90,000 $(-14.0)
(-525)
kWh
$(-167.0)
-
kW-mo/yr
- - $17,800
-
lb
-
TOTAL RECOMMENDED $90,077 $151,339 $19,501
729,180
kWh
$4,240
-
kW-mo/yr
$27,392 $21,072
-
MMBtu
$17,800
-
lb
$72
TOTAL IMPLEMENTED $38,725 $14,040 $9,378
350,617
kWh
$3,825
-
kW-mo/yr
$27,392 - - $(-1,870.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs