ITAC Assessment: WI0454
ITAC logo
ITAC Assessment: WI0454
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Compression and Injection-Molded Plastic
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 220
Plant Area 144,000
ft2
Annual Production 15,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Wisconsin
View Case Study

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $352,904 13,503,890
kWh
Electricity Demand $250,162 29,447
kW-mo/yr
Electricity Fees $72,122 -
Natural Gas $33,572 5,957
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $46,900 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $34,744

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $26,309 $61,875 $15,460
562,170
kWh
$10,849
-
kW-mo/yr
-
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $8,002 $24,500 $8,002
290,988
kWh
- -
03 2.4224: Upgrade controls on compressors $4,154 $10,500 $4,154
151,065
kWh
- -
04 2.6232: Install set-back timers $4,115 $400 - $4,115
-
kW-mo/yr
-
05 2.4221: Install compressor air intakes in coolest locations $3,128 $1,980 $1,697
61,683
kWh
$1,431
-
kW-mo/yr
-
06 2.7261: Install timers and/or thermostats $1,192 $1,600 - - $1,192
TOTAL RECOMMENDED $46,900 $100,855 $29,313
1,065,906
kWh
$16,395
-
kW-mo/yr
$1,192
TOTAL IMPLEMENTED $34,744 $65,855 $17,157
623,853
kWh
$16,395
-
kW-mo/yr
$1,192
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs