| Assessment Year | 2003 |
|---|---|
| Principal Product | Aggregate Processing Equipment |
| NAICS | 333131: Mining Machinery and Equipment Manufacturing |
| SIC | 3532: Mining Machinery and Equipment, Except Oil and Gas Field Machinery and Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 175 |
| Plant Area |
200,000
ft2
|
| Annual Production | 150
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $158,170 | 4,930,726 |
kWh
|
$0.032 |
| Electricity Demand | $105,108 | 10,156 |
kW-mo/yr
|
$10.35 |
| Electricity Fees | $30,396 | - |
|
- |
| Natural Gas | $146,343 | 31,868 |
MMBtu
|
$4.59 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $88,008 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $26,913 | $47,600 |
$16,362
482,664
kWh
|
$10,551
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4322: Use or replace with energy efficient substitutes | $16,417 | $29,500 |
$6,285
185,400
kWh
|
$10,132
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $14,045 | - | - |
$14,045
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.7261: Install timers and/or thermostats | $16,308 | $2,000 | - | - |
$16,308
-
MMBtu
|
- | - | |
| 05 | 3.6112: Use filter and drying oven to reduce sludge volume | $5,783 | $15,000 | - | - |
$(-881.0)
-
MMBtu
|
$6,664
-
gal
|
- | |
| 06 | 3.7137: Replace cloth rags with paper towels | $5,589 | - | - | - | - | - | $5,589 | |
| 07 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $2,048 | $3,500 |
$2,048
60,426
kWh
|
- | - | - | - | |
| 08 | 2.4221: Install compressor air intakes in coolest locations | $905 | $640 |
$610
17,995
kWh
|
- |
$295
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $88,008 | $98,240 |
$25,305
746,485
kWh
|
$34,728
-
kW-mo/yr
|
$15,722
-
MMBtu
|
$6,664
-
gal
|
$5,589 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs