ITAC Assessment: MA0058
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product COATED FABRICS &PLASTICS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 40
Plant Area
n/a
Annual Production 3,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $46,883 674,971
kWh
Natural Gas $64,395 9,822
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,828 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,828

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,060 $90 $1,060
15,240
kWh
-
02 2.2511: Insulate bare equipment $3,740 $5,760 - $3,740
-
MMBtu
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,028 - $1,028
14,654
kWh
-
TOTAL RECOMMENDED $5,828 $5,850 $2,088
29,894
kWh
$3,740
-
MMBtu
TOTAL IMPLEMENTED $5,828 $5,850 $2,088
29,894
kWh
$3,740
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs