ITAC Assessment: SU0177
ITAC logo
ITAC Assessment: SU0177
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Concrete, Sand & Gravel
NAICS 212321: Construction Sand and Gravel Mining
SIC 1442: Construction Sand and Gravel
Sales Range $1
M
to 5
M
# of Employees 32
Plant Area 19,324
ft2
Annual Production 365,996
ton
Production Hrs. Annual 1,200
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $55,140 935,550
kWh
Electricity Demand $22,199 6,534
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $340,263 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $321,467

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Administrative Changes Savings By-product Production Savings
01 2.8123: Pay utility bills on time $691 - - - $691 - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $85 - $36
600
kWh
$49
-
kW-mo/yr
- - -
03 2.4322: Use or replace with energy efficient substitutes $319,380 $270,000 $1,020
17,004
kWh
$360
-
kW-mo/yr
- $12,000 $306,000
04 2.4314: Use synthetic lubricant $1,396 $1,000 $1,331
22,183
kWh
$65
-
kW-mo/yr
- - -
05 2.8114: Change rate schedules or other changes in utility service $18,711 $134,000 - - - $18,711 -
TOTAL RECOMMENDED $340,263 $405,000 $2,387
39,787
kWh
$474
-
kW-mo/yr
$691 $30,711 $306,000
TOTAL IMPLEMENTED $321,467 $271,000 $2,351
39,187
kWh
$425
-
kW-mo/yr
$691 $12,000 $306,000
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs