Assessment Year | 2001 |
---|---|
Principal Product | Clutches |
NAICS |
n/a
|
SIC | 3449: Miscellaneous Structural Metal Work |
Sales Range | $5 M to 10M |
# of Employees | 57 |
Plant Area |
48,000
ft2
|
Annual Production | 580,000
pieces
|
Production Hrs. Annual | 4,900
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $51,920 | 896,880 |
kWh
|
$0.058 |
Electricity Demand | $10,704 | 1,038 |
kW-mo/yr
|
$10.31 |
Electricity Fees | $4,595 | - |
|
- |
Natural Gas | $25,256 | 3,021 |
MMBtu
|
$8.36 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $47,390 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.513: Re-arrange equipment layout to reduce labor costs | $26,600 | - | n/a | - | - | - | - | - | $26,600 | - | - |
02 | 3.8142: Distill contaminated solvents for reuse | $6,632 | $12,000 | n/a | - | - | - |
$9,100
-
gal
|
$(-476.0)
-
lb
|
$(-741.0) | - | $(-1,251.0) |
03 | 2.6218: Turn off equipment when not in use | $4,562 | $100 | n/a |
$4,562
115,200
kWh
|
- | - | - | - | - | - | - |
04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,796 | $3,760 | n/a |
$(-62.0)
(-1,574)
kWh
|
- |
$3,858
-
MMBtu
|
- | - | - | - | - |
05 | 2.7261: Install timers and/or thermostats | $4,274 | $600 | n/a | - | - |
$4,274
-
MMBtu
|
- | - | - | - | - |
06 | 3.7137: Replace cloth rags with paper towels | $751 | - | n/a | - | - | - | - | - | - | $751 | - |
07 | 2.4221: Install compressor air intakes in coolest locations | $486 | $640 | n/a |
$323
8,153
kWh
|
$163
-
kW-mo/yr
|
- | - | - | - | - | - |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $289 | - | n/a |
$192
4,857
kWh
|
$97
-
kW-mo/yr
|
- | - | - | - | - | - |
TOTAL RECOMMENDED | $47,390 | $17,100 |
$5,015
126,636
kWh
|
$260
-
kW-mo/yr
|
$8,132
-
MMBtu
|
$9,100
-
gal
|
$(-476.0)
-
lb
|
$25,859 | $751 | $(-1,251.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs