ITAC Assessment: WI0405
ITAC logo
ITAC Assessment: WI0405
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Actuators
NAICS
n/a
SIC 3593: Fluid Power Cylinders and Actuators
Sales Range $10
M
to 50
M
# of Employees 73
Plant Area 25,600
ft2
Annual Production 9,500
pieces
Production Hrs. Annual 4,250
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $18,929 579,200
kWh
Electricity Demand $17,455 1,692
kW-mo/yr
Electricity Fees $3,124 -
Natural Gas $13,341 1,579
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,682 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,890

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.6121: Reduce hot water temperature to the minimum required $5,787 $4,500 - - $5,787
-
MMBtu
- - - - -
02 2.6231: Utilize controls to operate equipment only when needed $2,749 $2,000 - - $2,749
-
MMBtu
- - - - -
03 3.3131: Use evaporation to concentrate material $3,585 $11,000 - - $(-183.0)
-
MMBtu
$4,968
-
gal
- $(-1,200.0) - -
04 3.6192: Use a less expensive method of waste removal $2,138 - - - - - $2,138
-
lb
- - -
05 2.7447: Install vinyl strip / high speed / air curtain doors $1,216 $500 $(-32.0)
(-933)
kWh
- $1,248
-
MMBtu
- - - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,839 $9,403 $1,102
31,939
kWh
$737
-
kW-mo/yr
- - - - - -
07 3.7137: Replace cloth rags with paper towels $759 - - - - - $(-18.0)
-
lb
- $777 -
08 2.4221: Install compressor air intakes in coolest locations $340 $640 $208
6,039
kWh
$132
-
kW-mo/yr
- - - - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $269 $570 $104
3,022
kWh
$34
-
kW-mo/yr
- - - - - $131
TOTAL RECOMMENDED $18,682 $28,613 $1,382
40,067
kWh
$903
-
kW-mo/yr
$9,601
-
MMBtu
$4,968
-
gal
$2,120
-
lb
$(-1,200.0) $777 $131
TOTAL IMPLEMENTED $11,890 $7,000 $(-32.0)
(-933)
kWh
- $9,784
-
MMBtu
- $2,138
-
lb
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs