| Assessment Year | 2000 |
|---|---|
| Principal Product | Printed Circuit Boards |
| NAICS |
n/a
|
| SIC | 3672: Printed Circuit Boards |
| Sales Range | $10 M to 50M |
| # of Employees | 215 |
| Plant Area |
128,000
ft2
|
| Annual Production | 1,000,000
pieces
|
| Production Hrs. Annual | 6,480
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $298,877 | 8,180,246 |
kWh
|
$0.037 |
| Electricity Demand | $256,251 | 18,267 |
kW-mo/yr
|
$14.03 |
| Electricity Fees | $17,275 | - |
|
- |
| Natural Gas | $91,931 | 26,064 |
MMBtu
|
$3.53 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $198,948 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 4.126: Install sensors to detect defects | $141,912 | $70,000 | - | - | - | $141,912 | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $18,107 | $20,000 |
$35,269
918,523
kWh
|
$19,779
-
kW-mo/yr
|
$(-36,941.0)
-
MMBtu
|
- | |
| 03 | 2.2437: Recover waste heat from equipment | $17,119 | $6,500 | - | - |
$17,119
-
MMBtu
|
- | |
| 04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $9,935 | $3,250 |
$8,709
226,846
kWh
|
$4,640
-
kW-mo/yr
|
$(-3,414.0)
-
MMBtu
|
- | |
| 05 | 2.7261: Install timers and/or thermostats | $5,952 | $1,000 | - | - |
$5,952
-
MMBtu
|
- | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $2,745 | $640 |
$1,824
47,479
kWh
|
$921
-
kW-mo/yr
|
- | - | |
| 07 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,623 | $1,033 | - | - |
$1,623
-
MMBtu
|
- | |
| 08 | 2.2511: Insulate bare equipment | $1,185 | $427 |
$774
20,223
kWh
|
$411
-
kW-mo/yr
|
- | - | |
| 09 | 2.2515: Use optimum thickness insulation | $370 | $375 | - | - |
$370
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $198,948 | $103,225 |
$46,576
1,213,071
kWh
|
$25,751
-
kW-mo/yr
|
$(-15,291.0)
-
MMBtu
|
$141,912 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs