ITAC Assessment: WI0376
ITAC logo
ITAC Assessment: WI0376
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Metal Stampings and Multi-Slides
NAICS
n/a
SIC 3469: Metal Stampings, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 87
Plant Area 52,335
ft2
Annual Production 10,000,000
pieces
Production Hrs. Annual 2,875
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $31,224 777,843
kWh
Electricity Demand $34,701 3,817
kW-mo/yr
Electricity Fees $3,765 -
Natural Gas $15,428 3,690
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $24,475 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.7261: Install timers and/or thermostats $3,857 $600 n/a - - $3,857
-
MMBtu
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $3,771 $10,971 n/a $2,185
52,462
kWh
$1,586
-
kW-mo/yr
- - -
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $3,131 - n/a - $3,131
-
kW-mo/yr
- - -
04 2.3132: Recharge batteries on during off-peak demand periods $1,172 $100 n/a - $1,172
-
kW-mo/yr
- - -
05 3.5315: Lease / purchase baler; sell cardboard to recycler $1,954 $1,000 n/a - - - $2,204
-
lb
$(-250.0)
06 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,719 $4,000 n/a $1,006
24,033
kWh
$713
-
kW-mo/yr
- - -
07 2.7241: Install outside air damper / economizer on hvac unit $1,375 $5,600 n/a $805
19,343
kWh
$570
-
kW-mo/yr
- - -
08 2.7243: Improve air circulation with destratification fans / other methods $1,691 $2,600 n/a $(-78.0)
(-1,758)
kWh
- $1,769
-
MMBtu
- -
09 2.7447: Install vinyl strip / high speed / air curtain doors $1,425 $1,124 n/a - - $1,425
-
MMBtu
- -
10 2.7447: Install vinyl strip / high speed / air curtain doors $912 $1,364 n/a - - $912
-
MMBtu
- -
11 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,109 $420 n/a $648
15,533
kWh
$461
-
kW-mo/yr
- - -
12 2.4221: Install compressor air intakes in coolest locations $685 $740 n/a $400
9,672
kWh
$285
-
kW-mo/yr
- - -
13 2.1123: Install automatic stack damper $904 $900 n/a - - $904
-
MMBtu
- -
14 2.4111: Utilize energy-efficient belts and other improved mechanisms $770 - n/a $323
7,620
kWh
$447
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $24,475 $29,419 $5,289
126,905
kWh
$8,365
-
kW-mo/yr
$8,867
-
MMBtu
$2,204
-
lb
$(-250.0)
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs