ITAC Assessment: WI0360
ITAC logo
ITAC Assessment: WI0360
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Gears, Housings, and Transmissions
NAICS
n/a
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 330
Plant Area 204,000
ft2
Annual Production 6,000
pieces
Production Hrs. Annual 7,200
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $414,768 12,349,942
kWh
Electricity Demand $345,447 24,400
kW-mo/yr
Electricity Fees $39,411 -
Natural Gas $231,605 75,965
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $96,242 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,133

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 3.1175: Use a different or recycled raw material $24,990 - - - - $(-10.0)
-
Tgal
- - - - $25,000
02 3.8142: Distill contaminated solvents for reuse $17,374 $22,500 - - - - $22,000
-
gal
$(-992.0)
-
lb
$(-1,980.0) $(-1,654.0) -
03 3.3131: Use evaporation to concentrate material $15,954 $16,000 - - $(-1,832.0)
-
MMBtu
- $20,786
-
gal
- $(-3,000.0) - -
04 2.7251: Reduce air conditioning load by evaporating water from roof $7,161 $40,800 $3,169
85,287
kWh
$4,169
-
kW-mo/yr
- $(-177.0)
-
Tgal
- - - - -
05 2.2621: Modify refrigeration system to operate at a lower pressure $2,661 $8,000 $1,744
46,893
kWh
$917
-
kW-mo/yr
- - - - - - -
06 2.2437: Recover waste heat from equipment $6,483 $1,000 - - $6,483
-
MMBtu
- - - - - -
07 2.4221: Install compressor air intakes in coolest locations $4,603 $640 $3,016
81,184
kWh
$1,587
-
kW-mo/yr
- - - - - - -
08 2.3132: Recharge batteries on during off-peak demand periods $5,510 $400 - $5,510
-
kW-mo/yr
- - - - - - -
09 3.2123: Convert to high volume low pressure (hvlp) paint guns $4,092 $500 - - - - - - - - $4,092
10 2.7135: Install occupancy sensors $2,640 $5,800 $1,325
35,756
kWh
$1,315
-
kW-mo/yr
- - - - - - -
11 2.7314: Reduce ventilation air $1,891 $500 $55
1,465
kWh
- $1,836
-
MMBtu
- - - - - -
12 2.7261: Install timers and/or thermostats $1,735 $400 - - $1,735
-
MMBtu
- - - - - -
13 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,148 $725 $623
16,706
kWh
$525
-
kW-mo/yr
- - - - - - -
TOTAL RECOMMENDED $96,242 $97,265 $9,932
267,291
kWh
$14,023
-
kW-mo/yr
$8,222
-
MMBtu
$(-187.0)
-
Tgal
$42,786
-
gal
$(-992.0)
-
lb
$(-4,980.0) $(-1,654.0) $29,092
TOTAL IMPLEMENTED $14,133 $7,200 $1,380
37,221
kWh
$6,825
-
kW-mo/yr
$1,836
-
MMBtu
- - - - - $4,092
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs