ITAC Assessment: LM0027
ITAC logo
ITAC Assessment: LM0027
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product tomato canning
NAICS
n/a
SIC 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies
Sales Range $10
M
to 50
M
# of Employees 85
Plant Area 24,600
ft2
Annual Production 34,600,000
lb
Production Hrs. Annual 4,992
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $60,464 1,363,200
kWh
Electricity Demand $11,043 1,356
kW-mo/yr
Electricity Fees $3,215 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $131,708 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,600

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Primary Product Savings
01 2.7121: Utilize daylight whenever possible in lieu of artificial light $16,547 - $15,222
112,740
kWh
$1,325
-
kW-mo/yr
- -
02 2.7122: Disconnect ballasts $199 $200 $199
1,472
kWh
- - -
03 4.611: Begin a practice of predictive / preventative maintenance $12,600 $1,000 - - $12,600 -
04 4.515: Install shelves / racks to utilize unused space $100,000 $28,080 - - - $100,000
05 4.522: Modify storage space to avoid rental of a warehouse $2,362 $520 - - $2,362 -
TOTAL RECOMMENDED $131,708 $29,800 $15,421
114,212
kWh
$1,325
-
kW-mo/yr
$14,962 $100,000
TOTAL IMPLEMENTED $12,600 $1,000 - - $12,600 -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs