Assessment Year | 2000 |
---|---|
Principal Product | flock transfers |
NAICS |
n/a
|
SIC | 2390: |
Sales Range | $5 M to 10M |
# of Employees | 100 |
Plant Area |
61,500
ft2
|
Annual Production | 25,000,000
pieces
|
Production Hrs. Annual | 4,368
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $21,041 | 1,238,277 |
kWh
|
$0.017 |
Electricity Demand | $46,544 | 3,565 |
kW-mo/yr
|
$13.06 |
Electricity Fees | $192 | - |
|
- |
Natural Gas | $30,266 | 7,155 |
MMBtu
|
$4.23 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $60,850 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $55,140 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $10,240 | $26,000 |
$5,010
301,290
kWh
|
$10,820
-
kW-mo/yr
|
$(-5,590.0)
-
MMBtu
|
- | - | - | - | - | - | |
02 | 2.3191: Use demand controller or load shedder | $4,710 | $7,500 | - |
$4,710
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
03 | 2.7314: Reduce ventilation air | $1,500 | $1,900 |
$80
4,982
kWh
|
$310
-
kW-mo/yr
|
$1,110
-
MMBtu
|
- | - | - | - | - | - | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $1,260 | $1,260 |
$400
24,033
kWh
|
$860
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
05 | 2.7224: Reduce space conditioning during non-working hours | $700 | $1,870 |
$160
9,965
kWh
|
$(-50.0)
-
kW-mo/yr
|
$590
-
MMBtu
|
- | - | - | - | - | - | |
06 | 2.7135: Install occupancy sensors | $310 | $900 |
$190
11,723
kWh
|
$120
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $200 | $410 |
$190
11,137
kWh
|
$400
-
kW-mo/yr
|
- | - | - | $(-390.0) | - | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $150 | - |
$410
24,326
kWh
|
$850
-
kW-mo/yr
|
- | - | - | $(-320.0) | - | $(-790.0) | - | |
09 | 3.5242: Recover metals from spent solutions and recycle | $800 | $250 | - | - | - | - |
$1,050
-
gal
|
- | - | $(-250.0) | - | |
10 | 3.4154: Eliminate leaks in water lines and valves | $190 | $300 | - | - |
$40
-
MMBtu
|
$70
-
Tgal
|
- | - | - | - |
$80
-
Tgal
|
|
11 | 4.446: Automate finishing process | $37,380 | $30,000 | - | - | - | - | - | $18,690 | - | $18,690 | - | |
12 | 2.8113: Purchase gas directly from a contract gas supplier | $3,410 | $500 | - | - | - | - | - | - | $3,410 | - | - | |
TOTAL RECOMMENDED | $60,850 | $70,890 |
$6,440
387,456
kWh
|
$18,020
-
kW-mo/yr
|
$(-3,850.0)
-
MMBtu
|
$70
-
Tgal
|
$1,050
-
gal
|
$17,980 | $3,410 | $17,650 |
$80
-
Tgal
|
||
TOTAL IMPLEMENTED | $55,140 | $68,240 |
$6,360
382,474
kWh
|
$17,710
-
kW-mo/yr
|
$(-4,960.0)
-
MMBtu
|
$70
-
Tgal
|
- | $17,980 | - | $17,900 |
$80
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs