ITAC Assessment: WI0326
ITAC logo
ITAC Assessment: WI0326
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Printed Circuit Boards
NAICS
n/a
SIC 3672: Printed Circuit Boards
Sales Range $10
M
to 50
M
# of Employees 210
Plant Area 57,000
ft2
Annual Production 1,300,000
pieces
Production Hrs. Annual 6,300
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $223,243 5,145,956
kWh
Electricity Demand $127,298 10,416
kW-mo/yr
Electricity Fees $1,321 -
Natural Gas $12,756 2,939
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $126,547 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
01 3.4114: Replace city water with recycled water via cooling tower $52,640 $25,000 $(-995.0)
(-11,430)
kWh
- - $54,135
-
Tgal
- - $(-500.0)
02 3.3132: Use reverse osmosis to concentrate material $43,913 $40,000 - - - $45,113
-
Tgal
- - $(-1,200.0)
03 2.3191: Use demand controller or load shedder $11,269 $20,000 - $11,269
-
kW-mo/yr
- - - - -
04 2.7251: Reduce air conditioning load by evaporating water from roof $7,874 $12,186 $4,390
91,735
kWh
$3,866
-
kW-mo/yr
- $(-382.0)
-
Tgal
- - -
05 3.7131: Use a rag recycle service $4,430 - - - - - $680
-
lb
$3,750 -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,348 $12,500 $3,348
70,047
kWh
- - - - - -
07 2.4221: Install compressor air intakes in coolest locations $1,948 $740 $1,341
28,136
kWh
$607
-
kW-mo/yr
- - - - -
08 2.7261: Install timers and/or thermostats $504 $400 - - $504
-
MMBtu
- - - -
09 2.2511: Insulate bare equipment $321 $46 $200
4,103
kWh
$121
-
kW-mo/yr
- - - - -
10 3.6113: Remove sludge from tanks on a regular basis $300 - - - - - $300
-
lb
- -
TOTAL RECOMMENDED $126,547 $110,872 $8,284
182,591
kWh
$15,863
-
kW-mo/yr
$504
-
MMBtu
$98,866
-
Tgal
$980
-
lb
$3,750 $(-1,700.0)
TOTAL IMPLEMENTED - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs