| Assessment Year | 1998 |
|---|---|
| Principal Product | Printed Circuit Boards |
| NAICS |
n/a
|
| SIC | 3672: Printed Circuit Boards |
| Sales Range | $10 M to 50M |
| # of Employees | 210 |
| Plant Area |
57,000
ft2
|
| Annual Production | 1,300,000
pieces
|
| Production Hrs. Annual | 6,300
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $223,243 | 5,145,956 |
kWh
|
$0.043 |
| Electricity Demand | $127,298 | 10,416 |
kW-mo/yr
|
$12.22 |
| Electricity Fees | $1,321 | - |
|
- |
| Natural Gas | $12,756 | 2,939 |
MMBtu
|
$4.34 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $126,547 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.4114: Replace city water with recycled water via cooling tower | $52,640 | $25,000 |
$(-995.0)
(-11,430)
kWh
|
- | - |
$54,135
-
Tgal
|
- | - | $(-500.0) | |
| 02 | 3.3132: Use reverse osmosis to concentrate material | $43,913 | $40,000 | - | - | - |
$45,113
-
Tgal
|
- | - | $(-1,200.0) | |
| 03 | 2.3191: Use demand controller or load shedder | $11,269 | $20,000 | - |
$11,269
-
kW-mo/yr
|
- | - | - | - | - | |
| 04 | 2.7251: Reduce air conditioning load by evaporating water from roof | $7,874 | $12,186 |
$4,390
91,735
kWh
|
$3,866
-
kW-mo/yr
|
- |
$(-382.0)
-
Tgal
|
- | - | - | |
| 05 | 3.7131: Use a rag recycle service | $4,430 | - | - | - | - | - |
$680
-
lb
|
$3,750 | - | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,348 | $12,500 |
$3,348
70,047
kWh
|
- | - | - | - | - | - | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $1,948 | $740 |
$1,341
28,136
kWh
|
$607
-
kW-mo/yr
|
- | - | - | - | - | |
| 08 | 2.7261: Install timers and/or thermostats | $504 | $400 | - | - |
$504
-
MMBtu
|
- | - | - | - | |
| 09 | 2.2511: Insulate bare equipment | $321 | $46 |
$200
4,103
kWh
|
$121
-
kW-mo/yr
|
- | - | - | - | - | |
| 10 | 3.6113: Remove sludge from tanks on a regular basis | $300 | - | - | - | - | - |
$300
-
lb
|
- | - | |
| TOTAL RECOMMENDED | $126,547 | $110,872 |
$8,284
182,591
kWh
|
$15,863
-
kW-mo/yr
|
$504
-
MMBtu
|
$98,866
-
Tgal
|
$980
-
lb
|
$3,750 | $(-1,700.0) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs