ITAC Assessment: WI0289
ITAC logo
ITAC Assessment: WI0289
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Packaging Paper and Film
NAICS
n/a
SIC 2571:
Sales Range $10
M
to 50
M
# of Employees 180
Plant Area 114,750
ft2
Annual Production 25,200,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $345,751 9,726,553
kWh
Electricity Demand $283,333 22,049
kW-mo/yr
Electricity Fees $39,508 -
Natural Gas $293,610 90,175
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $63,993 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $35,780

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 3.6193: Install equipment (eg compactor) to reduce disposal costs $17,900 - - - - - $17,900
-
lb
- - - -
02 4.212: Adopt in-house material generation $12,690 - - - - - - - - $12,690 -
03 2.7447: Install vinyl strip / high speed / air curtain doors $12,496 $11,150 $(-349.0)
(-9,379)
kWh
- $12,845
-
MMBtu
- - - - - -
04 2.2621: Modify refrigeration system to operate at a lower pressure $7,349 $22,000 $2,025
54,220
kWh
$5,324
-
kW-mo/yr
- - - - - - -
05 2.7251: Reduce air conditioning load by evaporating water from roof $6,780 $34,425 $4,744
126,905
kWh
$5,359
-
kW-mo/yr
- $(-3,323.0)
-
Tgal
- - - - -
06 3.8142: Distill contaminated solvents for reuse $1,430 - - - - - - $(-3,000.0) $(-200.0) - $4,630
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,219 $150 $1,599
42,790
kWh
$620
-
kW-mo/yr
- - - - - - -
08 2.4221: Install compressor air intakes in coolest locations $1,588 $640 $1,020
27,257
kWh
$568
-
kW-mo/yr
- - - - - - -
09 2.3132: Recharge batteries on during off-peak demand periods $1,541 $5,000 - $973
-
kW-mo/yr
- - - - $568 - -
TOTAL RECOMMENDED $63,993 $73,365 $9,039
241,793
kWh
$12,844
-
kW-mo/yr
$12,845
-
MMBtu
$(-3,323.0)
-
Tgal
$17,900
-
lb
$(-3,000.0) $368 $12,690 $4,630
TOTAL IMPLEMENTED $35,780 $5,150 $1,599
42,790
kWh
$1,593
-
kW-mo/yr
- - $17,900
-
lb
$(-3,000.0) $368 $12,690 $4,630
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs