Assessment Year | 1996 |
---|---|
Principal Product | Overhead cranes |
NAICS |
n/a
|
SIC | 3536: Overhead Traveling Cranes, Hoists, and Monorail Systems |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
105,400
ft2
|
Annual Production | 60
pieces
|
Production Hrs. Annual | 5,750
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $116,708 | 2,055,686 |
kWh
|
$0.057 |
Electricity Demand | $50,115 | 5,766 |
kW-mo/yr
|
$8.69 |
Electricity Fees | $(-875.0) | - |
|
- |
Natural Gas | $32,737 | 7,387 |
MMBtu
|
$4.43 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $28,092 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,667 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $8,188 | - | - |
$8,188
-
kW-mo/yr
|
- | - | - | |
02 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $6,400 | $3,000 | - | - | - |
$6,400
-
gal
|
- | |
03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $4,517 | $4,434 | - | - |
$4,517
-
MMBtu
|
- | - | |
04 | 2.7243: Improve air circulation with destratification fans / other methods | $2,736 | $3,150 |
$(-147.0)
(-4,689)
kWh
|
- |
$2,883
-
MMBtu
|
- | - | |
05 | 3.3122: Use filtration, centrifuging to remove contaminants | $1,200 | $7,000 | - | - | - | - |
$1,200
-
gal
|
|
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,466 | $486 |
$1,115
24,619
kWh
|
$351
-
kW-mo/yr
|
- | - | - | |
07 | 2.7135: Install occupancy sensors | $446 | $300 |
$446
14,361
kWh
|
- | - | - | - | |
08 | 2.7261: Install timers and/or thermostats | $959 | $400 | - | - |
$959
-
MMBtu
|
- | - | |
09 | 3.8121: Cover containers to minimize evaporative losses | $928 | $1,000 | - | - | - | - |
$928
-
gal
|
|
10 | 2.4221: Install compressor air intakes in coolest locations | $657 | $740 |
$263
12,896
kWh
|
$394
-
kW-mo/yr
|
- | - | - | |
11 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $451 | - |
$177
5,862
kWh
|
$274
-
kW-mo/yr
|
- | - | - | |
12 | 2.4133: Use most efficient type of electric motors | $144 | $585 |
$71
2,345
kWh
|
$73
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $28,092 | $21,095 |
$1,925
55,394
kWh
|
$9,280
-
kW-mo/yr
|
$8,359
-
MMBtu
|
$6,400
-
gal
|
$2,128
-
gal
|
||
TOTAL IMPLEMENTED | $8,667 | $4,811 |
$1,449
39,860
kWh
|
$818
-
kW-mo/yr
|
- |
$6,400
-
gal
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs