Assessment Year | 1996 |
---|---|
Principal Product | RV Components |
NAICS |
n/a
|
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $10 M to 50M |
# of Employees | 350 |
Plant Area |
130,000
ft2
|
Annual Production | 150,000
pieces
|
Production Hrs. Annual | 4,400
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $272,261 | 3,690,211 |
kWh
|
$0.074 |
Electricity Demand | $104,690 | 8,634 |
kW-mo/yr
|
$12.13 |
Electricity Fees | $11,333 | - |
|
- |
Natural Gas | $73,445 | 30,800 |
MMBtu
|
$2.38 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $23,210 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,078 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.6232: Install set-back timers | $15,994 | $1,600 | - | - |
$15,994
-
MMBtu
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,781 | $2,212 |
$1,055
24,033
kWh
|
$726
-
kW-mo/yr
|
- | - | |
03 | 3.4116: Meter recycled water (to reduce sewer charges) | $1,600 | $1,000 | - | - | - |
$1,600
-
Tgal
|
|
04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,542 | $1,400 | - | - |
$1,542
-
MMBtu
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $820 | $1,280 |
$514
11,723
kWh
|
$306
-
kW-mo/yr
|
- | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $755 | $210 |
$475
10,844
kWh
|
$280
-
kW-mo/yr
|
- | - | |
07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $718 | - | - |
$718
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $23,210 | $7,702 |
$2,044
46,600
kWh
|
$2,030
-
kW-mo/yr
|
$17,536
-
MMBtu
|
$1,600
-
Tgal
|
||
TOTAL IMPLEMENTED | $4,078 | $3,822 |
$1,530
34,877
kWh
|
$1,006
-
kW-mo/yr
|
$1,542
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs