| Assessment Year | 2017 |
|---|---|
| Principal Product | Aeration water treatment system |
| NAICS | 333413: Industrial and Commercial Fan and Blower and Air Purification Equipment Manufacturing |
| SIC | 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment |
| Sales Range | $50 M to 100M |
| # of Employees | 225 |
| Plant Area |
56,000
ft2
|
| Annual Production | 100,000
units
|
| Production Hrs. Annual | 7,776
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $178,171 | 3,125,990 |
kWh
|
$0.057 | |
| Electricity Demand | $100,374 | 6,666 |
kW-mo/yr
|
$15.06 | |
| Natural Gas | $17,934 | 1,907 |
MMBtu
|
$9.40 | |
| Waste Disposal Costs | |||||
| Water Usage | $802 | 80 |
Tgal
|
$10.06 | |
| TOTAL YEARLY COSTS | $297,281 | ||||
| RECOMMENDED SAVINGS* | $23,309 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $21,413 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,978 | $27,450 |
$10,651
186,857
kWh
|
$4,351
-
kW-mo/yr
|
- | - | $976 | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,308 | - |
$1,308
22,939
kWh
|
- | - | - | - | |
| 03 | 3.4151: Minimize water usage | $199 | $30 | - | - | - |
$199
-
Tgal
|
- | |
| 04 | 2.7425: Clean or color roof to reduce solar load | $1,896 | $6,500 |
$1,896
33,278
kWh
|
- | - | - | - | |
| 05 | 2.2511: Insulate bare equipment | $3,927 | $1,050 | - | - |
$3,927
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $23,309 | $35,030 |
$13,855
243,074
kWh
|
$4,351
-
kW-mo/yr
|
$3,927
-
MMBtu
|
$199
-
Tgal
|
$976 | ||
| TOTAL IMPLEMENTED | $21,413 | $28,530 |
$11,959
209,796
kWh
|
$4,351
-
kW-mo/yr
|
$3,927
-
MMBtu
|
$199
-
Tgal
|
$976 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs