| Assessment Year | 1994 |
|---|---|
| Principal Product | Printed Circuit Boards |
| NAICS |
n/a
|
| SIC | 3672: Printed Circuit Boards |
| Sales Range | $10 M to 50M |
| # of Employees | 70 |
| Plant Area |
42,000
ft2
|
| Annual Production | 500,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $205,513 | 3,106,389 |
kWh
|
$0.066 |
| Natural Gas | $98,688 | 22,941 |
MMBtu
|
$4.30 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $25,833 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,872 | $25,010 | n/a |
$11,872
179,367
kWh
|
- |
| 02 | 2.7135: Install occupancy sensors | $2,286 | $1,153 | n/a |
$2,286
34,584
kWh
|
- |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $207 | $340 | n/a |
$207
3,224
kWh
|
- |
| 04 | 2.4133: Use most efficient type of electric motors | $2,395 | $2,054 | n/a |
$2,395
36,342
kWh
|
- |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $626 | $3,044 | n/a |
$626
9,379
kWh
|
- |
| 06 | 2.2695: Use cascade system of recirculating during cold weather to avoid sub-cooling | $4,008 | $12,000 | n/a |
$4,008
60,668
kWh
|
- |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $749 | $500 | n/a |
$749
11,430
kWh
|
- |
| 08 | 2.4314: Use synthetic lubricant | $1,758 | $2,330 | n/a |
$1,758
12,016
kWh
|
- |
| 09 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,932 | $2,000 | n/a | - |
$1,932
-
MMBtu
|
| TOTAL RECOMMENDED | $25,833 | $48,431 |
$23,901
347,010
kWh
|
$1,932
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs