Assessment Year | 1990 |
---|---|
Principal Product | SCREWS |
NAICS |
n/a
|
SIC | 3452: Bolts, Nuts, Screws, Rivets, and Washers |
Sales Range | $10 M to 50M |
# of Employees | 170 |
Plant Area |
n/a
|
Annual Production | 1,000,000
pieces
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $261,743 | 2,922,919 |
kWh
|
$0.090 |
Natural Gas | $59,187 | 11,015 |
MMBtu
|
$5.37 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $48,709 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $36,906 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.8113: Purchase gas directly from a contract gas supplier | $30,592 | $500 | - |
$30,592
-
MMBtu
|
|
02 | 2.7243: Improve air circulation with destratification fans / other methods | $5,728 | $5,806 |
$(-604.0)
(-6,741)
kWh
|
$6,332
-
MMBtu
|
|
03 | 2.3191: Use demand controller or load shedder | $5,580 | $10,000 |
$5,580
-
kWh
|
- | |
04 | 2.7261: Install timers and/or thermostats | $3,371 | $1,500 | - |
$3,371
-
MMBtu
|
|
05 | 2.4221: Install compressor air intakes in coolest locations | $1,928 | $1,000 |
$1,928
21,688
kWh
|
- | |
06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $495 | $600 | - |
$495
-
MMBtu
|
|
07 | 2.7494: Install storm windows and doors | $344 | $1,134 | - |
$344
-
MMBtu
|
|
08 | 2.6232: Install set-back timers | $386 | $400 |
$386
4,396
kWh
|
- | |
09 | 2.6121: Reduce hot water temperature to the minimum required | $285 | - | - |
$285
-
MMBtu
|
|
TOTAL RECOMMENDED | $48,709 | $20,940 |
$7,290
19,343
kWh
|
$41,419
-
MMBtu
|
||
TOTAL IMPLEMENTED | $36,906 | $4,534 |
$2,314
26,084
kWh
|
$34,592
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs