Assessment Year | 1990 |
---|---|
Principal Product | ALUMINUM & ZINC CASTINGS |
NAICS |
n/a
|
SIC | 3363: Aluminum Die-Castings |
Sales Range | $10 M to 50M |
# of Employees | 90 |
Plant Area |
n/a
|
Annual Production | 2,500,000
pieces
|
Production Hrs. Annual | 4,250
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $316,958 | 4,213,365 |
kWh
|
$0.075 |
Natural Gas | $137,208 | 41,610 |
MMBtu
|
$3.30 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $29,093 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,023 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $23,340 | - |
$25,740
-
kWh
|
- | $(-2,400.0) | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,910 | $2,000 |
$2,910
-
kWh
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $705 | $1,328 |
$705
9,379
kWh
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $930 | $2,000 |
$930
12,309
kWh
|
- | - | |
05 | 2.6232: Install set-back timers | $730 | $600 |
$730
9,672
kWh
|
- | - | |
06 | 2.7261: Install timers and/or thermostats | $478 | $250 | - |
$478
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $29,093 | $6,178 |
$31,015
31,360
kWh
|
$478
-
MMBtu
|
$(-2,400.0) | ||
TOTAL IMPLEMENTED | $5,023 | $5,578 |
$4,545
21,688
kWh
|
$478
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs