ITAC Assessment: WI0059
ITAC logo
ITAC Assessment: WI0059
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product VINYL FLOORING
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 205
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 6,600
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $264,863 5,822,978
kWh
Natural Gas $179,743 38,364
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $41,509 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $22,190

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4312: Improve lubrication practices $12,658 - $12,658
278,429
kWh
-
02 2.6218: Turn off equipment when not in use $8,983 $800 - $8,983
-
MMBtu
03 2.2414: Use waste heat from hot flue gases to preheat $7,916 $5,000 - $7,916
-
MMBtu
04 2.2437: Recover waste heat from equipment $5,025 $3,000 - $5,025
-
MMBtu
05 2.3132: Recharge batteries on during off-peak demand periods $2,400 $3,750 $2,400
-
kWh
-
06 2.4221: Install compressor air intakes in coolest locations $1,517 $2,000 $1,517
33,411
kWh
-
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,374 - $1,374
30,188
kWh
-
08 2.7447: Install vinyl strip / high speed / air curtain doors $929 $1,000 - $929
-
MMBtu
09 2.6232: Install set-back timers $449 $400 $449
9,965
kWh
-
10 2.2511: Insulate bare equipment $258 $175 $305
6,741
kWh
$(-47.0)
-
MMBtu
TOTAL RECOMMENDED $41,509 $16,125 $18,703
358,734
kWh
$22,806
-
MMBtu
TOTAL IMPLEMENTED $22,190 $11,550 $5,291
63,599
kWh
$16,899
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs