ITAC Assessment: UM0295
ITAC logo
ITAC Assessment: UM0295
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Hot Forgings of Steel for Auto Industry
NAICS 332111: Iron and Steel Forging
SIC 3462: Iron and Steel Forgings
Sales Range $50
M
to 100
M
# of Employees 172
Plant Area 158,500
ft2
Annual Production 30,000
ton
Production Hrs. Annual 7,200
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $790,053 25,440,568
kWh
Electricity Demand $518,627 46,220
kW-mo/yr
Electricity Fees $72,945 -
Natural Gas $453,338 63,385
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $202,678 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $87,178

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Consumption Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $80,138 $170,000 $50,012
1,610,712
kWh
$30,126
-
kW-mo/yr
- - -
02 2.3212: Optimize plant power factor $71,400 $75,000 - - $71,400 - -
03 3.4156: Use flow control valves on equipment to optimize water use $15,365 $1,130 - - - - $15,365
-
Tgal
04 2.7243: Improve air circulation with destratification fans / other methods $10,656 $5,250 $(-224.0)
(-7,202)
kWh
$(-162.0)
-
kW-mo/yr
- $11,042
-
MMBtu
-
05 2.7447: Install vinyl strip / high speed / air curtain doors $8,859 $2,400 - - - $8,859
-
MMBtu
-
06 2.4221: Install compressor air intakes in coolest locations $7,040 $1,200 $4,394
141,500
kWh
$2,646
-
kW-mo/yr
- - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $4,767 $13,877 $1,975
63,706
kWh
$2,792
-
kW-mo/yr
- - -
08 2.2414: Use waste heat from hot flue gases to preheat $2,259 $3,080 - - - $2,259
-
MMBtu
-
09 2.2511: Insulate bare equipment $1,316 $1,860 - - - $1,316
-
MMBtu
-
10 2.7134: Use photocell controls $878 $736 $878
28,326
kWh
- - - -
TOTAL RECOMMENDED $202,678 $274,533 $57,035
1,837,042
kWh
$35,402
-
kW-mo/yr
$71,400 $23,476
-
MMBtu
$15,365
-
Tgal
TOTAL IMPLEMENTED $87,178 $171,200 $54,406
1,752,212
kWh
$32,772
-
kW-mo/yr
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs