Assessment Year | 2005 |
---|---|
Principal Product | Silicone Products |
NAICS | 336350: Motor Vehicle Transmission and Power Train Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $10 M to 50M |
# of Employees | 94 |
Plant Area |
32,000
ft2
|
Annual Production | 14,100,000
pieces
|
Production Hrs. Annual | 4,680
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $88,810 | 2,568,289 |
kWh
|
$0.035 |
Electricity Demand | $71,733 | 7,410 |
kW-mo/yr
|
$9.68 |
Electricity Fees | $7,099 | - |
|
- |
Natural Gas | $9,099 | 1,556 |
MMBtu
|
$5.85 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $10,942 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,776 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,386 | $10,000 |
$2,896
83,741
kWh
|
$2,490
-
kW-mo/yr
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,865 | $150 |
$1,195
34,572
kWh
|
$670
-
kW-mo/yr
|
- | |
03 | 2.6231: Utilize controls to operate equipment only when needed | $1,004 | $400 |
$329
5,218
kWh
|
- |
$675
-
MMBtu
|
|
04 | 2.2437: Recover waste heat from equipment | $895 | $1,000 | - | - |
$895
-
MMBtu
|
|
05 | 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas | $656 | - |
$656
18,928
kWh
|
- | - | |
06 | 2.7314: Reduce ventilation air | $616 | $150 |
$616
9,477
kWh
|
- | - | |
07 | 2.7124: Make a practice of turning off lights when not needed | $159 | $25 |
$60
1,723
kWh
|
$99
-
kW-mo/yr
|
- | |
08 | 2.4221: Install compressor air intakes in coolest locations | $141 | $300 |
$91
2,618
kWh
|
$50
-
kW-mo/yr
|
- | |
09 | 2.7444: Close holes and openings in building such as broken windows | $130 | $50 |
$13
200
kWh
|
- |
$117
-
MMBtu
|
|
10 | 2.7135: Install occupancy sensors | $90 | $600 |
$90
2,608
kWh
|
- | - | |
TOTAL RECOMMENDED | $10,942 | $12,675 |
$5,946
159,085
kWh
|
$3,309
-
kW-mo/yr
|
$1,687
-
MMBtu
|
||
TOTAL IMPLEMENTED | $9,776 | $11,325 |
$5,842
156,267
kWh
|
$3,259
-
kW-mo/yr
|
$675
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs