ITAC Assessment: UM0009
ITAC logo
ITAC Assessment: UM0009
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Metal Finishing
NAICS
n/a
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $1
M
to 5
M
# of Employees 145
Plant Area 60,000
ft2
Annual Production 10,000,000
pieces
Production Hrs. Annual 6,600
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $180,384 1,671,454
kWh
Natural Gas $93,117 18,581
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $140,640 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $39,342

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4133: Use most efficient type of electric motors $7,936 $6,420 $7,936
73,564
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $13,061 $18,721 $13,061
121,043
kWh
-
03 2.4221: Install compressor air intakes in coolest locations $262 $800 $262
2,345
kWh
-
04 2.6231: Utilize controls to operate equipment only when needed $2,513 $1,500 $2,513
23,154
kWh
-
05 2.3412: Use waste heat to produce steam to drive a steam turbine-generator $88,700 $330,000 $88,700
725,381
kWh
-
06 2.2514: Cover open tanks $4,163 $2,440 - $4,163
-
MMBtu
07 2.2414: Use waste heat from hot flue gases to preheat $760 $932 - $760
-
MMBtu
08 2.1243: Use heat from boiler blowdown to preheat boiler feed water $9,325 $6,000 - $9,325
-
MMBtu
09 2.2136: Install / repair insulation on steam lines $930 $196 - $930
-
MMBtu
10 2.7447: Install vinyl strip / high speed / air curtain doors $4,829 $1,500 - $4,829
-
MMBtu
11 2.7231: Use radiant heater for spot heating $8,161 $21,400 - $8,161
-
MMBtu
TOTAL RECOMMENDED $140,640 $389,909 $112,472
945,487
kWh
$28,168
-
MMBtu
TOTAL IMPLEMENTED $39,342 $51,477 $21,259
196,952
kWh
$18,083
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs