ITAC Assessment: UK1313
ITAC logo
ITAC Assessment: UK1313
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product aluminum
NAICS 331314: Secondary Smelting and Alloying of Aluminum
SIC 3341: Secondary Smelting and Refining of Nonferrous Metals
Sales Range greater than $500
M
# of Employees 125
Plant Area 215,000
ft2
Annual Production 650,000,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,874,900 41,952,645
kWh
Electricity Demand $531,844 74,906
kW-mo/yr
Electricity Fees $330,390 -
Natural Gas $3,011,174 977,916
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $450,522 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $320,647

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
01 2.7121: Utilize daylight whenever possible in lieu of artificial light $396 $5,000 $396
8,794
kWh
- - - -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $841 - $841
18,693
kWh
- - - -
03 2.4113: Install motor voltage controller on lightly loaded motors $23,080 $10,000 $23,080
512,888
kWh
- - - -
04 2.4239: Eliminate or reduce compressed air usage $3,510 $5,000 $3,510
77,997
kWh
- - - -
05 2.4239: Eliminate or reduce compressed air usage $5,528 $205 $4,511
100,247
kWh
$1,017
-
kW-mo/yr
- - -
06 2.4226: Use / purchase optimum sized compressor $74,025 $55,000 - - - - $74,025
07 2.6218: Turn off equipment when not in use $7,011 - $7,011
155,805
kWh
- - - -
08 2.6231: Utilize controls to operate equipment only when needed $2,313 - $2,313
51,393
kWh
- - - -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,246 $3,000 $6,755
150,116
kWh
$1,491
-
kW-mo/yr
- - -
10 2.4231: Reduce the pressure of compressed air to the minimum required $695 - $567
12,600
kWh
$128
-
kW-mo/yr
- - -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $2,284 $15,000 $107
2,373
kWh
$23
-
kW-mo/yr
$2,154 - -
12 2.6218: Turn off equipment when not in use $20,092 - $20,092
446,481
kWh
- - - -
13 2.6231: Utilize controls to operate equipment only when needed $10,444 $4,500 $10,444
232,076
kWh
- - - -
14 2.4151: Develop a repair/replace policy $3,770 $9,750 $3,028
67,773
kWh
$742
-
kW-mo/yr
- - -
15 2.7142: Utilize higher efficiency lamps and/or ballasts $913 $2,119 $749
16,644
kWh
$164
-
kW-mo/yr
- - -
16 2.2511: Insulate bare equipment $6,807 $894 - - - $6,807
-
MMBtu
-
17 2.2442: Preheat combustion air with waste heat $1,679 $5,000 - - - $1,679
-
MMBtu
-
18 2.1113: Reduce combustion air flow to optimum $21,538 $2,500 - - - $21,538
-
MMBtu
-
19 2.1116: Improve combustion control capability $252,538 $210,000 - - - $252,538
-
MMBtu
-
20 2.2424: Use heat in flue gases to preheat products or materials $412 - - - - $412
-
MMBtu
-
21 3.1193: Convert from batch operation to continuous processing $4,400 - - - - $4,400
-
MMBtu
-
TOTAL RECOMMENDED $450,522 $327,968 $83,404
1,853,880
kWh
$3,565
-
kW-mo/yr
$2,154 $287,374
-
MMBtu
$74,025
TOTAL IMPLEMENTED $320,647 $254,750 $60,378
1,342,197
kWh
$765
-
kW-mo/yr
$2,154 $257,350
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs