ITAC Assessment: UF0654
ITAC logo
ITAC Assessment: UF0654
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Industrial Valve MAnufacturing
NAICS 332911: Industrial Valve Manufacturing
SIC 3491: Industrial Valves
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 44,168
ft2
Annual Production 166,802
units
Production Hrs. Annual 4,160
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $80,682 851,280
kWh
Electricity Demand $26,433 3,912
kW-mo/yr
Electricity Fees $30,893 -
TOTAL YEARLY COSTS $138,008
RECOMMENDED SAVINGS* $293,598 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings
01 2.9114: Use solar heat to make electricty $83,684 $322,608 $57,737
607,763
kWh
$25,947
-
kW-mo/yr
- -
02 2.4226: Use / purchase optimum sized compressor $18,934 $52,105 $(-747.0)
(-7,860)
kWh
$(-319.0)
-
kW-mo/yr
- $20,000
03 2.3191: Use demand controller or load shedder $8,047 $4,580 $6,065
63,846
kWh
$1,982
-
kW-mo/yr
- -
04 2.6231: Utilize controls to operate equipment only when needed $7,021 $25,440 $7,021
73,902
kWh
- - -
05 2.2623: Minimize condenser cooling water temperature $1,912 $8,477 $1,912
20,171
kWh
- - -
06 4.446: Automate finishing process $120,507 $105,000 $(-3,952.0)
(-41,600)
kWh
$(-811.0)
-
kW-mo/yr
$91,520 $33,750
07 4.424: Improve space comfort conditioning $53,493 $12,420 $(-1,177.0)
(-12,413)
kWh
$(-242.0)
-
kW-mo/yr
$54,912 -
TOTAL RECOMMENDED $293,598 $530,630 $66,859
703,809
kWh
$26,557
-
kW-mo/yr
$146,432 $53,750
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs