ITAC Assessment: UM0419
ITAC logo
ITAC Assessment: UM0419
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Shipping containers for the automotive industry
NAICS 332439: Other Metal Container Manufacturing
SIC 3412: Metal Shipping Barrels, Drums, Kegs, and Pails
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 1,000,000
ft2
Annual Production 15,000
pieces
Production Hrs. Annual 2,500
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $117,227 853,301
kWh
Natural Gas $13,055 1,254
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,551 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $2,593 $200 $2,593
18,874
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,967 $4,350 $2,967
21,600
kWh
-
03 2.2428: Use flue gases in radiant heater for space heating, ovens, etc $9,991 - - $9,991
-
MMBtu
TOTAL RECOMMENDED $15,551 $4,550 $5,560
40,474
kWh
$9,991
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs