Assessment Year | 2024 |
---|---|
Principal Product | Circuit Boards Assembly and Test |
NAICS | 334418: Printed Circuit Assembly (Electronic Assembly) Manufacturing |
SIC | 3679: Electronic Components, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
52,000
ft2
|
Annual Production | 319,000
units
|
Production Hrs. Annual | 4,250
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $119,852 | 1,239,226 |
kWh
|
$0.097 |
Electricity Demand | $44,608 | 3,722 |
kW-mo/yr
|
$11.98 |
Electricity Fees | $25,514 | - |
|
- |
TOTAL YEARLY COSTS | $189,974 | |||
RECOMMENDED SAVINGS* | $667,871 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.3191: Use demand controller or load shedder | $16,482 | $6,000 |
$12,021
123,923
kWh
|
$4,461
-
kW-mo/yr
|
- | |
02 | 2.6231: Utilize controls to operate equipment only when needed | $11,318 | $25,440 |
$8,357
86,158
kWh
|
$2,961
-
kW-mo/yr
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,655 | $13,445 |
$7,899
81,431
kWh
|
$2,756
-
kW-mo/yr
|
- | |
04 | 2.7232: Replace existing hvac unit with high efficiency model | $7,989 | $36,000 |
$5,105
52,631
kWh
|
$2,884
-
kW-mo/yr
|
- | |
05 | 2.7425: Clean or color roof to reduce solar load | $3,458 | $9,470 |
$3,458
35,654
kWh
|
- | - | |
06 | 2.2623: Minimize condenser cooling water temperature | $1,257 | $5,940 |
$1,257
12,960
kWh
|
- | - | |
07 | 2.4239: Eliminate or reduce compressed air usage | $1,007 | - |
$1,007
10,379
kWh
|
- | - | |
08 | 2.4224: Upgrade controls on compressors | $705 | $1,252 |
$705
7,265
kWh
|
- | - | |
09 | 4.446: Automate finishing process | $315,000 | $181,056 | - | - | $315,000 | |
10 | 4.112: Replace old machine with new automatic multi-station tool | $300,000 | $183,056 | - | - | $300,000 | |
TOTAL RECOMMENDED | $667,871 | $461,659 |
$39,809
410,401
kWh
|
$13,062
-
kW-mo/yr
|
$615,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs