ITAC Assessment: CO0600
ITAC logo
ITAC Assessment: CO0600
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Pet toys
NAICS 326299: All Other Rubber Product Manufacturing
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 50,000
ft2
Annual Production 3,500,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $36,101 970,400
kWh
Electricity Demand $36,250 2,418
kW-mo/yr
Electricity Fees $341 -
Natural Gas $97,590 12,720
MMBtu
Fuel Oil #2 $20,000 8,500
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,450 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,400

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.6218: Turn off equipment when not in use $5,230 $1,140 $5,230
137,500
kWh
- - - -
02 2.4226: Use / purchase optimum sized compressor $2,710 $150 $770
20,100
kWh
$1,940
-
kW-mo/yr
- - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $620 $60 $260
6,700
kWh
$360
-
kW-mo/yr
- - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $400 $190 $220
5,800
kWh
$180
-
kW-mo/yr
- - -
05 2.4225: Install common header on compressors $320 $3,450 $140
3,600
kWh
$180
-
kW-mo/yr
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $4,770 $12,130 $2,090
55,000
kWh
$2,580
-
kW-mo/yr
- $130 $(-30.0)
07 2.9114: Use solar heat to make electricty $1,560 $11,000 $560
14,600
kWh
$1,000
-
kW-mo/yr
- - -
08 2.7243: Improve air circulation with destratification fans / other methods $1,050 $6,160 $(-190.0)
(-4,900)
kWh
$(-110.0)
-
kW-mo/yr
$1,350
-
MMBtu
- -
09 2.7492: Use proper thickness of insulation on building envelope $790 - $790
20,800
kWh
- - - -
TOTAL RECOMMENDED $17,450 $34,280 $9,870
259,200
kWh
$6,130
-
kW-mo/yr
$1,350
-
MMBtu
$130 $(-30.0)
TOTAL IMPLEMENTED $6,400 $14,850 $2,740
71,600
kWh
$3,660
-
kW-mo/yr
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs