Assessment Year | 2009 |
---|---|
Principal Product | transformer |
NAICS | 334416: Capacitor, Resistor, Coil, Transformer, and Other Inductor Manufacturing |
SIC | 3677: Electronic Coils, Transformers, and Other Inductors |
Sales Range | $10 M to 50M |
# of Employees | 32 |
Plant Area |
285,700
ft2
|
Annual Production | 150
units
|
Production Hrs. Annual | 5,880
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,690,426 | 38,955,022 |
kWh
|
$0.043 |
Natural Gas | $320,850 | 122,421 |
MMBtu
|
$2.62 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $107,479 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $107,479 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $45,616 | $42,000 | - |
$45,616
-
MMBtu
|
|
02 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $60,170 | $43,800 | - |
$60,170
-
MMBtu
|
|
03 | 2.7135: Install occupancy sensors | $1,693 | $1,780 |
$1,693
42,000
kWh
|
- | |
TOTAL RECOMMENDED | $107,479 | $87,580 |
$1,693
42,000
kWh
|
$105,786
-
MMBtu
|
||
TOTAL IMPLEMENTED | $107,479 | $87,580 |
$1,693
42,000
kWh
|
$105,786
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs