Assessment Year | 2020 |
---|---|
Principal Product | Chemicals and Chemical Preparations |
NAICS | 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing |
SIC | 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 180 |
Plant Area |
8,820
ft2
|
Annual Production | 13,215,390
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $298,975 | 5,128,303 |
kWh
|
$0.058 |
Electricity Demand | $75,529 | 8,914 |
kW-mo/yr
|
$8.47 |
Electricity Fees | $15,915 | - |
|
- |
TOTAL YEARLY COSTS | $390,419 | |||
RECOMMENDED SAVINGS* | $51,892 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $675 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $18,774 | $11,876 |
$15,346
263,252
kWh
|
$3,428
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,308 | $21,823 |
$9,512
163,165
kWh
|
$2,296
-
kW-mo/yr
|
$500 | |
03 | 2.4133: Use most efficient type of electric motors | $6,899 | $28,466 |
$5,819
99,816
kWh
|
$1,080
-
kW-mo/yr
|
- | |
04 | 2.7135: Install occupancy sensors | $6,004 | $7,027 |
$6,004
102,980
kWh
|
- | - | |
05 | 2.7423: Reduce heat gain by window tinting | $5,105 | $19,291 |
$2,798
48,000
kWh
|
$2,307
-
kW-mo/yr
|
- | |
06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,216 | $30 |
$631
10,820
kWh
|
$585
-
kW-mo/yr
|
- | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $805 | $135 |
$686
11,763
kWh
|
$119
-
kW-mo/yr
|
- | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $675 | $122 |
$572
9,811
kWh
|
$103
-
kW-mo/yr
|
- | |
09 | 2.4224: Upgrade controls on compressors | $106 | $394 |
$90
1,542
kWh
|
$16
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $51,892 | $89,164 |
$41,458
711,149
kWh
|
$9,934
-
kW-mo/yr
|
$500 | ||
TOTAL IMPLEMENTED | $675 | $122 |
$572
9,811
kWh
|
$103
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs