ITAC Assessment: UF0576
ITAC logo
ITAC Assessment: UF0576
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Bread and donuts
NAICS 311999: All Other Miscellaneous Food Manufacturing
SIC 2099: Food Preparations, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 20
Plant Area 132,000
ft2
Annual Production 36,687
units
Production Hrs. Annual 8,736
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $712,337 9,517,300
kWh
Electricity Demand $78,424 16,061
kW-mo/yr
Electricity Fees $24,770 -
Natural Gas $335,377 54,726
MMBtu
Waste Disposal Costs
Water Usage $506 250
Tgal
TOTAL YEARLY COSTS $1,151,414
RECOMMENDED SAVINGS* $477,190 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $473,464

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Raw Material Savings
01 2.3191: Use demand controller or load shedder $55,456 $51,203 $49,966
666,211
kWh
$5,490
-
kW-mo/yr
- - -
02 2.1213: Direct warmest air to combustion intake $30,987 $10,183 - - $30,987
-
MMBtu
- -
03 2.4133: Use most efficient type of electric motors $29,479 $16,283 $26,999
359,983
kWh
$2,480
-
kW-mo/yr
- - -
04 2.7243: Improve air circulation with destratification fans / other methods $21,495 $6,314 $(-161.4)
(-2,152)
kWh
$(-103.1)
-
kW-mo/yr
- $21,760 -
05 2.6231: Utilize controls to operate equipment only when needed $16,965 $25,427 $16,965
226,198
kWh
- - - -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $6,147 - $5,931
79,076
kWh
- - $101 $115
07 2.4222: Install adequate dryers on air lines to eliminate blowdown $5,306 $765 $5,306
70,750
kWh
- - - -
08 2.1222: Install turbulators $3,726 $7,500 - - $3,726
-
MMBtu
- -
09 2.7447: Install vinyl strip / high speed / air curtain doors $1,828 $2,002 - - $1,828
-
MMBtu
- -
10 2.2121: Increase amount of condensate returned $1,400 $1,449 - - $1,400
-
MMBtu
- -
11 4.662: Level one – add communication using iiot devices to existing control system to modify operations $284,508 - - - - $284,508 -
12 4.424: Improve space comfort conditioning $19,893 $5,851 $(-1,481.0)
(-19,740)
kWh
$(-386.0)
-
kW-mo/yr
- $21,760 -
TOTAL RECOMMENDED $477,190 $126,977 $103,525
1,380,326
kWh
$7,481
-
kW-mo/yr
$37,941
-
MMBtu
$328,129 $115
TOTAL IMPLEMENTED $473,464 $119,477 $103,525
1,380,326
kWh
$7,481
-
kW-mo/yr
$34,215
-
MMBtu
$328,129 $115
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs