| Assessment Year | 2008 |
|---|---|
| Principal Product | Electrical meter sockets and related components, powder coating |
| NAICS | 335931: Current-Carrying Wiring Device Manufacturing |
| SIC | 3643: Current-Carrying Wiring Devices |
| Sales Range | $10 M to 50M |
| # of Employees | 190 |
| Plant Area |
96,000
ft2
|
| Annual Production | 230,000
pieces
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $154,114 | 2,583,568 |
kWh
|
$0.060 |
| Natural Gas | $151,960 | 18,795 |
MMBtu
|
$8.09 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $7,606 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,032 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.1135: Repair furnaces and oven doors so that they seal efficiently | $62 | $200 | - |
$62
-
MMBtu
|
|
| 02 | 2.1122: Re-size charging openings or add a movable door on equipment | $222 | $1,400 | - |
$222
-
MMBtu
|
|
| 03 | 2.2515: Use optimum thickness insulation | $34 | $300 | - |
$34
-
MMBtu
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,936 | $1,400 |
$2,936
43,300
kWh
|
- | |
| 05 | 2.2447: Heat water with exhaust heat | $4,352 | $10,000 | - |
$4,352
-
MMBtu
|
|
| TOTAL RECOMMENDED | $7,606 | $13,300 |
$2,936
43,300
kWh
|
$4,670
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $3,032 | $1,900 |
$2,936
43,300
kWh
|
$96
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs