ITAC Assessment: MZ0025
ITAC logo
ITAC Assessment: MZ0025
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Electrical meter sockets and related components, powder coating
NAICS 335931: Current-Carrying Wiring Device Manufacturing
SIC 3643: Current-Carrying Wiring Devices
Sales Range $10
M
to 50
M
# of Employees 190
Plant Area 96,000
ft2
Annual Production 230,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $154,114 2,583,568
kWh
Natural Gas $151,960 18,795
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,606 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,032

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.1135: Repair furnaces and oven doors so that they seal efficiently $62 $200 - $62
-
MMBtu
02 2.1122: Re-size charging openings or add a movable door on equipment $222 $1,400 - $222
-
MMBtu
03 2.2515: Use optimum thickness insulation $34 $300 - $34
-
MMBtu
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,936 $1,400 $2,936
43,300
kWh
-
05 2.2447: Heat water with exhaust heat $4,352 $10,000 - $4,352
-
MMBtu
TOTAL RECOMMENDED $7,606 $13,300 $2,936
43,300
kWh
$4,670
-
MMBtu
TOTAL IMPLEMENTED $3,032 $1,900 $2,936
43,300
kWh
$96
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs