Assessment Year | 2011 |
---|---|
Principal Product | Milk, Juice, Tea, Water |
NAICS | 311511: Fluid Milk Manufacturing |
SIC | 2026: Fluid Milk |
Sales Range | $50 M to 100M |
# of Employees | 114 |
Plant Area |
135,000
ft2
|
Annual Production | 36,000,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,100,107 | 15,474,296 |
kWh
|
$0.071 |
Electricity Demand | $370,867 | 61,602 |
kW-mo/yr
|
$6.02 |
Natural Gas | $47,488 | 25,311 |
MMBtu
|
$1.88 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $266,278 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $60,249 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7124: Make a practice of turning off lights when not needed | $1,607 | - |
$1,607
22,636
kWh
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $38,731 | $42,492 |
$34,375
484,149
kWh
|
$4,356
-
kW-mo/yr
|
- | |
03 | 2.4226: Use / purchase optimum sized compressor | $9,454 | $38,200 |
$9,454
99,520
kWh
|
- | - | |
04 | 2.7229: Air condition only space necessary | $4,722 | $550 |
$4,722
66,501
kWh
|
- | - | |
05 | 2.7261: Install timers and/or thermostats | $562 | $75 |
$562
5,918
kWh
|
- | - | |
06 | 2.7224: Reduce space conditioning during non-working hours | $19,349 | $2,235 |
$19,349
203,670
kWh
|
- | - | |
07 | 2.6231: Utilize controls to operate equipment only when needed | $106,353 | $25,300 |
$106,353
1,497,934
kWh
|
- | - | |
08 | 2.2135: Repair and eliminate steam leaks | $156 | $370 | - | - |
$156
-
MMBtu
|
|
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $80,522 | $8,600 |
$80,522
847,600
kWh
|
- | - | |
10 | 2.4131: Size electric motors for peak operating efficiency | $4,822 | $670 |
$4,822
67,914
kWh
|
- | - | |
TOTAL RECOMMENDED | $266,278 | $118,492 |
$261,766
3,295,842
kWh
|
$4,356
-
kW-mo/yr
|
$156
-
MMBtu
|
||
TOTAL IMPLEMENTED | $60,249 | $44,802 |
$55,893
716,373
kWh
|
$4,356
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs