Assessment Year | 2010 |
---|---|
Principal Product | Printed Material |
NAICS | 323111: Commercial Printing (except Screen and Books) |
SIC | 2759: Commercial Printing, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 154 |
Plant Area |
45,960
ft2
|
Annual Production | 2,760,000
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $271,882 | 3,869,640 |
kWh
|
$0.070 |
Electricity Demand | $141,868 | 10,918 |
kW-mo/yr
|
$12.99 |
Electricity Fees | $51,432 | - |
|
- |
Natural Gas | $49,999 | 4,320 |
MMBtu
|
$11.57 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $55,119 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7447: Install vinyl strip / high speed / air curtain doors | $7,679 | $4,000 |
$7,679
71,108
kWh
|
- | - | |
02 | 2.7243: Improve air circulation with destratification fans / other methods | $20,263 | $4,600 |
$20,263
187,626
kWh
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,562 | $5,039 |
$7,066
99,216
kWh
|
$2,496
-
kW-mo/yr
|
- | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $457 | - |
$301
3,484
kWh
|
$156
-
kW-mo/yr
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $3,443 | $4,200 |
$3,443
47,825
kWh
|
- | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,608 | $469 |
$1,608
14,891
kWh
|
- | - | |
07 | 2.4235: Remove or close off unneeded compressed air lines | $4,197 | $1,979 |
$4,197
38,860
kWh
|
- | - | |
08 | 2.4156: Establish a preventative maintenance program | $3,387 | $1,200 |
$3,387
31,369
kWh
|
- | - | |
09 | 2.8113: Purchase gas directly from a contract gas supplier | $4,523 | - | - | - | $4,523 | |
TOTAL RECOMMENDED | $55,119 | $21,487 |
$47,944
494,379
kWh
|
$2,652
-
kW-mo/yr
|
$4,523 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs