Assessment Year | 2025 |
---|---|
Principal Product | manufactures Steel, Chrome Iron and High Alloy casting |
NAICS | 331513: Steel Foundries (except Investment) |
SIC | 3325: Steel Foundries, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 131 |
Plant Area |
250,000
ft2
|
Annual Production | 1,606
ton
|
Production Hrs. Annual | 4,576
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $726,963 | 8,552,100 |
kWh
|
$0.085 |
Electricity Demand | $126,567 | 49,845 |
kW-mo/yr
|
$2.54 |
Electricity Fees | $62,076 | - |
|
- |
Natural Gas | $160,074 | 36,719 |
MMBtu
|
$4.36 |
LPG | $64,287 | 3,321 |
MMBtu
|
$19.36 |
TOTAL YEARLY COSTS | $1,139,967 | |||
RECOMMENDED SAVINGS* | $240,196 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $7,008 | $2,000 |
$7,008
82,451
kWh
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,874 | $2,600 |
$4,633
54,519
kWh
|
$241
-
kW-mo/yr
|
- | - | |
03 | 2.2443: Re-use or recycle hot or cold process exhaust air | $26,110 | $14,500 | - | - | - |
$26,110
-
MMBtu
|
|
04 | 2.4221: Install compressor air intakes in coolest locations | $10,210 | $8,000 |
$9,619
113,174
kWh
|
$591
-
kW-mo/yr
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,423 | $5,658 |
$6,015
70,761
kWh
|
$408
-
kW-mo/yr
|
- | - | |
06 | 2.7135: Install occupancy sensors | $702 | $660 |
$702
8,255
kWh
|
- | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $24,044 | $45,000 |
$22,850
268,829
kWh
|
$1,194
-
kW-mo/yr
|
- | - | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $11,365 | $24,074 |
$10,683
125,686
kWh
|
$682
-
kW-mo/yr
|
- | - | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,935 | $14,078 |
$5,579
65,636
kWh
|
$356
-
kW-mo/yr
|
- | - | |
10 | 2.1336: Install equipment to utilize waste fuel | $90,409 | $240,000 | - | - |
$90,409
-
MMBtu
|
- | |
11 | 2.1331: Burn a less expensive grade of fuel | $49,500 | $160,000 | - | - |
$(-14,388.0)
-
MMBtu
|
$63,888
-
MMBtu
|
|
12 | 2.7234: Use heat pump for space conditioning | $3,616 | $14,943 |
$3,463
40,754
kWh
|
$153
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $240,196 | $531,513 |
$70,552
830,065
kWh
|
$3,625
-
kW-mo/yr
|
$76,021
-
MMBtu
|
$89,998
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs