Assessment Year | 2008 |
---|---|
Principal Product | PVC pipe |
NAICS | 326122: Plastics Pipe and Pipe Fitting Manufacturing |
SIC | 3084: Plastics Pipe |
Sales Range | $50 M to 100M |
# of Employees | 120 |
Plant Area |
140,500
ft2
|
Annual Production | 130,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,214,967 | 18,261,600 |
kWh
|
$0.067 |
Electricity Demand | $321,252 | 34,773 |
kW-mo/yr
|
$9.24 |
Electricity Fees | $48,398 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $349,571 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $74,953 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #1 Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $20,962 | $1,500 |
$20,962
303,798
kWh
|
- | - | - | - | |
02 | 2.4225: Install common header on compressors | $4,076 | $2,560 |
$4,076
59,069
kWh
|
- | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,047 | $1,060 |
$3,047
35,027
kWh
|
- | - | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,106 | - |
$4,106
47,197
kWh
|
- | - | - | - | |
05 | 2.4239: Eliminate or reduce compressed air usage | $1,900 | $800 |
$1,900
21,845
kWh
|
- | - | - | - | |
06 | 2.7261: Install timers and/or thermostats | $16,637 | $30,850 |
$12,465
180,648
kWh
|
$4,172
-
kW-mo/yr
|
- | - | - | |
07 | 2.8227: Adjust / maintain fork lift trucks for most efficient operation | $3,791 | - | - | - |
$3,791
-
MMBtu
|
- | - | |
08 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $39,146 | $1,589 |
$39,146
567,336
kWh
|
- | - | - | - | |
09 | 2.7124: Make a practice of turning off lights when not needed | $7,856 | $809 |
$7,856
113,848
kWh
|
- | - | - | - | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,945 | $34,619 |
$12,092
169,944
kWh
|
$1,853
-
kW-mo/yr
|
- | - | - | |
11 | 2.7135: Install occupancy sensors | $5,889 | $6,806 |
$5,889
85,350
kWh
|
- | - | - | - | |
12 | 2.4151: Develop a repair/replace policy | $729 | - |
$729
5,481
kWh
|
- | - | - | - | |
13 | 2.4133: Use most efficient type of electric motors | $48,442 | $82,588 |
$47,460
531,529
kWh
|
$982
-
kW-mo/yr
|
- | - | - | |
14 | 2.8118: Check for accuracy of utility / power meters | $170,526 | $5,967 |
$169,011
2,121,072
kWh
|
$1,515
-
kW-mo/yr
|
- | - | - | |
15 | 3.7311: Maintain machines to reduce leaks | $6,175 | $161 | - | - | - | - | $6,175 | |
16 | 3.4133: Clean fouling from water lines regularly | $2,344 | $7,838 | - | - | - | $2,344 | - | |
TOTAL RECOMMENDED | $349,571 | $177,147 |
$328,739
4,242,144
kWh
|
$8,522
-
kW-mo/yr
|
$3,791
-
MMBtu
|
$2,344 | $6,175 | ||
TOTAL IMPLEMENTED | $74,953 | $21,623 |
$62,643
887,956
kWh
|
- |
$3,791
-
MMBtu
|
$2,344 | $6,175 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #1 Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs