Assessment Year | 1989 |
---|---|
Principal Product | WHEELS & BLOWERS |
NAICS |
n/a
|
SIC | 3498: Fabricated Pipe and Pipe Fittings |
Sales Range | $5 M to 10M |
# of Employees | 130 |
Plant Area |
n/a
|
Annual Production | 65,000
pieces
|
Production Hrs. Annual | 2,040
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $110,597 | 1,665,885 |
kWh
|
$0.066 |
Natural Gas | $117,876 | 28,720 |
MMBtu
|
$4.10 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $24,490 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,809 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $3,618 | $1,000 | - |
$3,618
-
MMBtu
|
- | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,453 | - |
$2,453
-
kWh
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,150 | $4,000 |
$2,656
39,859
kWh
|
$(-506.0)
-
MMBtu
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $791 | $1,000 |
$977
14,654
kWh
|
$(-186.0)
-
MMBtu
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $356 | $75 |
$432
5,275
kWh
|
- | $(-76.0) | |
06 | 2.7492: Use proper thickness of insulation on building envelope | $9,331 | $25,000 | - |
$9,331
-
MMBtu
|
- | |
07 | 3.4115: Recover and reuse cooling water | $5,791 | $20,000 |
$596
5,275
kWh
|
- | $5,195 | |
TOTAL RECOMMENDED | $24,490 | $51,075 |
$7,114
65,063
kWh
|
$12,257
-
MMBtu
|
$5,119 | ||
TOTAL IMPLEMENTED | $2,809 | $75 |
$2,885
5,275
kWh
|
- | $(-76.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs